An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Early Delivery SystemsStatus Daryl Cote TPTF

  2. Release 3 – State Estimator and Telemetry Sep Oct Nov Dec Jan 2008 2007 Feb E1 R2 ICCP Fail-over / P2P SE Verification E2 R3 R3: SE / Telemetry Criteria (SE Tuning) Legend: % in parentheses are from the 11/05 TPTF update TPTF

  3. Convergence Rate Non-business hours tolerance is set to 50MW / 75MVar TPTF

  4. Observability Status Reported to ROS on Feb 14th and emphasized the need to complete this effort ASAP TPTF

  5. Release 4 – NMMS / NOMCR Sep Oct Nov Dec Jan 2008 2007 Feb Network Model Verification NOMCR Checkout E2 R4 R4: NOMCR / Network Model verification • Start of EDS 2 - R4 NOMCR has been moved to start the week of 3/17/2008 • NMMS became available in a “Sandbox” environment enabling market participants to become familiar with the system 1/28/2008 • NMMS/NOMCR overview training has been completed by the market participants • Citrix connections and digital certificates have been successfully installed and validated for 100% of the market participants • MOD on Demand module became available in a “Sandbox” for planners • Access have been granted and validated with the market participants to use PTC and MOD application functionalities • Testing scenarios and acceptance testing are currently in the development phase • Market participants have been scheduled to attend CIM class on 2/26/08 • Quick reference materials and users guide on how to use the system, create and maintain projects, and change requests were distributed to the market participants • A narrated web-based version of the NMMS course and training material are now available on lineat: http://nodal.ercot.com/training/courses/nc09.html#materials TPTF

  6. Release 4 – NMMS / NOMCR TPTF

  7. Release 5 - SCED Sep Oct Nov Dec Jan 2008 2007 Feb 6-month LMP Posting RT ICCP E3 R5 SCED R5.1 SCED R5.2 SCED R5.3: RT ICCP SCED R5.4: LMP Post Legend: % in parentheses are from the 1/21 TPTF update TPTF

  8. SPPs –West 345Kv Hub Invalid CC Configuration 02/9 02/10 2/11 02/12 02/13 Given sufficient inputs the output of SCED are reasonable and can be sustained over a period of time. TPTF

  9. LMP Reasonableness • Market Operations presented a document to TPTF at the Nov 5&6th meeting on reasonableness. • The document described preconditions of data accuracy and system functionality and a few basic scenarios to validate the system including: • No constraints are activated - All nodes will have the same final LMP • No constraints are activated and GTBD (Generation to be dispatched) is increased - All nodes will have the same final LMP but will be higher than the LMP in the case with lower GTBD • A single constraint is activated – The LMP at the nodes with negative Shift Factor will be higher than LMP at the nodes with positive Shift Factor • All constraints are competitive - no price mitigation is done on the offer curves TPTF

  10. This covers scenario 1 through 4 TPTF

  11. Supporting Data for Scenarios TPTF

  12. Release 6 - LFC Jan Feb Mar Apr May 2008 Jun E3 R6 R6.1: ACE & RLC R6.2: QSE Testing R6.3: TST Link for LFC Documents & Status: http://nodal.ercot.com/readiness/eds3/documents/index.html Legend: % in parentheses are from the 1/21 TPTF update TPTF

  13. Release 6 – LFC Phase I Testing Status • Phase II WebEx on Wednesday February 27th at 1:30 PM • Phase III Testing Workshop March 14th 9:00 AM at the Met Center Austin • Prior to March 15th QSEs need to provide accurate & continuous values for: Regulation Up, down, RR, & Non-spin Responsibility, RR & Non-spin Schedules, Participation Factors, Raise & Lower block status LFC email Address: LFC@ERCOT.COM TPTF

  14. Release 7.1 - CRR Dec 07 Dec 07 Dec 07 Jan 08 Jan 08 Jan 08 Feb 08 Feb 08 Feb 08 Mar 08 Mar 08 Mar 08 Apr 08 Apr 08 Apr 08 May 08 May 08 May 08 CRR CRR – – R7.0 R7.0 CRR CRR – – R7.1 R7.1 CRR CRR – – R7.2 R7.2 CRR CRR – – R7.3 R7.3 CRR CRR – – R7.4 R7.4 CRR CRR – – R7.5 (TBD) R7.5 (TBD) R7.1 (UI Connectivity) started on schedule on Feb 4th Strong progress enabled early completion of R7.1 on Feb 13th Kicked-off R7.2 (fully structured monthly allocation/auction) on schedule on Feb 18th Nominations being submitted this week Bid submission and bilateral trade activity next two weeks TPTF

  15. EDS 4 Release 9.1 Jan Feb Mar Apr May 2008 Jun E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT R9.3: Outage Scheduler The next two weeks are the peak demand for support calls and we believe we have staff to cover it. Only 5 QSEs are scheduled for support calls after March 5th (minus those that have not signed up) Legend: % in parentheses are from the 1/21 TPTF update TPTF

  16. Ambridge Energy Aquila Bear Energy* Brilliant Energy Citadel Energy Products Clearview Electric ECONnergy Electric Now Glacial Energy Kansas City Power and Light Lehman Brothers Commodity Services Merrill Lynch Commodities MxEnergy Electric Inc QSE National Power Company Sitara Energy Spark Energy Texas Retail Energy Texpo Power Urban Energy Source WCW International EDS 4 Release 9.1 QSEs that have not signed up for a testing window for EDS4 (as of COB 2/20/08) 3 Market Notices sent to date and Client Services continuing to contact Account Executives TPTF

  17. EDS Deliverables        168 Hour Test plan and cut-over approach are being developed and plan to discuss with TPTF in late March  Legend: indicates completion TPTF

  18. Questions? TPTF