An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDS 1Early Delivery Systems EDS 1 TPTF Update Jonathan Pulcini - Project Manager August 28, 2007

  2. EDS 1 – Early Delivery Systems Point to Point Verification Testing • PtP Testing Update • PtP Issue Resolution Process • Short Term (for EDS 1) • Long Term (beyond EDS 1) • PtP Issues Report • EDS 1 Testing Deliverables • EDS 1 Testing Metrics • Ongoing Process • Remaining Schedule • Questions EDS 1 – Release 2

  3. EDS 1 – PtP Testing Update EDS 1 – Release 2

  4. EDS 1 – PtP Testing Update • Currently, the error rate is at 4 % for PtP testing. • All issues represent an mix of both ERCOT and MP issues. • Errors consist of both modeling and telemetry type errors encountered during PtP testing. • Errors are prioritized, categorized, and assigned to either the modeling team or telemetry teams to address as issues in a issues database. • For Non-Field Telemetered point Quality Code errors (category E-NFT) , ERCOT will re-verify selected points of various device types with each MP (up to 10 %) once the ERCOT EMS upgrade is available in Sept. • ERCOT is working with the vendor to deliver a fix for the E-NFT category errors by mid Sept. • ERCOT is targeting to resolve all issues for a rate of 3 % or less for each MP by the end of Release 2 (Sept. 30th). EDS 1 – Release 2

  5. EDS 1 – PtP Issue Resolution Process (Short Term) • Each issue is entered into an issue database in a Pending status. • MPs are provided with an issue list after their PtP testing is completed. • Each issue is Assigned to ERCOT and/or the MP and categorized as a Modeling or Telemetry issue type. • Each issue is investigated and resolved accordingly; some issues can require a Service Request be submitted by the MP to complete. • Each issue is re-tested to ensure correction was made before it is migrated to Production. • Once an issue has been resolved, tested, and migrated to Production, it is Closed. • The MP is provided an updated Issue List on a periodic basis to continue to address remaining issues. EDS 1 – Release 2

  6. EDS 1 – Issue Resolution Process (Long Term) SCADA / NOM Data Issues Management • Definition • Nodal EMS will provide tools to measure SCADA and SE performance • Performance measurements are based on Telemetry and SE Standards • SCADA not performing to standards will be: • reported using ERCOT Enterprise Data Warehouse functionality • available to ERCOT and to the responsible MP via the MIS portal • resolved jointly between ERCOT Operations Support and the MPs • Conclusion • Operations Support will need a Data Issues Management Tool • Short term to resolve p2p issues • Long term to resolve on-going performance issues ERCOT I C C P p2p Issue Mgmt MPs EMS EDW EDS 1 – Release 2

  7. EDS 1 – Issue Resolution Process (Long Term) SCADA / NOM Data Issues Management Basic Tool Requirements • SCADA / NOM issues creation • import issues from EDW or other sources (current PtP issue DB) • Manage a list of ERCOT and MP contacts with contact information • Notify ERCOT and MPs when issues are Assigned, Updated, Closed • Manage and track issues • Pending (new issue) • Assigned (to MP and/or ERCOT) • To Implement (Service Request created and linked) • Closed (issue resolved, verified and closed in Production for both Zonal and Nodal) • Include a Web-based thin client • Include Reporting and Trend Analysis • Provide Secure access • ERCOT has access to all issues • MPs can access only their assigned issues EDS 1 – Release 2

  8. EDS 1 – Testing Issues Report EDS 1 – Release 2

  9. EDS 1 – Testing Issues Report EDS 1 – Release 2

  10. EDS 1 – Testing Deliverables EDS 1 – Release 2

  11. EDS 1 – Early Delivery Systems EDS 1 – Release 2

  12. EDS 1 – Readiness Metrics For a MP to be considered ready and marked as such in the Readiness Metrics for EDS 1, they must have the following completed by the end of Release 2: • PtP Testing has been completed. • Complete Telemetry check and topology review. • Failover testing has been completed. • Complete association failover test – ICCP link failover to alternate server. • Resolve all issues down to 3% or less for modeling and telemetry for each MP. • Address all priority modeling and telemetry issues. • Includes re-test of selected points categorized as E-NFT quality code issues (up to 10%). EDS 1 – Release 2

  13. EDS 2 – Early Delivery Systems EDS 1 Release 2 – Entry Criteria Status EDS 1 – Release 2

  14. EDS 2 – Early Delivery Systems EDS 1 Release 2 – Exit Criteria Status EDS 1 – Release 2

  15. EDS 1 – Ongoing Process • What will the new process be for telemetry checking beyond EDS 1? • The PtP process established and used for telemetry checking in EDS 1 will be used for all new construction or changes being submitted by a MP in the future. • Each new substation or generation resource will not only include a modeling check but also a PtP telemetry checkout to ensure accuracy and reliability. • Telemetry check will be scheduled as part of a checklist to energize a new station/resource. • Any issues encountered will be logged in current issues DB and resolved by following the existing processes. EDS 1 – Release 2

  16. EDS 1 – Remaining Schedule • Complete testing of 99% all remaining points by Sept 30th; 100% by early Oct. • Log all issues and address them accordingly with each MP through the current issue assignment and resolution process. • Complete internal alarm processing and testing. • Complete site failover testing by Sept. 30th for each MP; includes both ICCP association failover (primary to secondary link) and server disaster recovery testing. • Verify with each MP that issues have been resolved to 3 % or less by Sept. 30th. EDS 1 – Release 2

  17. Questions? • Testing • Issue Resolution Process • Deliverables • Metrics • Schedule EDS 1 – Release 2