5/27/2012 7:59:28 PM. . . . . . . 1996. 1997. J F M A M J J A S O N D. . J F M A M J J A S O N D. . . MD Phase 1. MD Phase 2. 1998. J F M A. Phase 1Define System ArchitectureEstablish Baseline Project PlanMD Inter-agency Team establishedMD CVISN Objectives establishedCarri
E N D
1. 5/28/2012 5:52:36 AM Maryland CVISN Program PlanTable of Contents 1 Executive Summary
2 Introduction
3 Program Objectives & Project Descriptions
4 Program Requirements and Design
5 Program Work Breakdown Structure
6 Organization Structure
7 Work Assignments
8 Procurement Strategy
9 Program Processes
10 Phases and Critical Milestones
11 Funding Resources and Program Budget
12 Products
13 Program Issues to be Resolved
Appendix A: Point of Contact List
Appendix B: CVISN Acronyms & Program Definitions
Appendix C: COACH Part 2 Checklist 10.1 Program Phase Chart
10.2 Major Program Milestones
10.3 Project Build Charts
2. 5/28/2012 5:52:36 AM
3. 5/28/2012 5:52:36 AM
4. 5/28/2012 5:52:36 AM
5. 5/28/2012 5:52:36 AM 10.2 Major Program Milestones Nov 98 (Jul 98) First safety information exchange pairwise interface interoperability test execution
Feb 99 (Jun 98) First credentials administration pairwise interface interoperability test execution
Feb 99 (Feb 99) Safety Scenario Demonstration - Industry Day
Nov 99 (Sep 99) Initial Perryville E-Screening Capability
Nov 99 (Nov 99) Revised MD Top-Level Design Description
Jan 00 (Nov 99) Revised MD Program Plan Jan 00 MD CVISN Prototype complete; transition e-credentialing and safety info exchange projects to agency budgets
Mar 00 (Dec 99) Perryville E-screening Build 2 complete
Jun 00 MD CVISN Level 1 Complete
Jul 00 Perryville E-screening Build 3 complete
Nov 00 Perryville E-screening Build 4 complete
6. 5/28/2012 5:52:36 AM 10.3 Project Build Charts
7. 5/28/2012 5:52:36 AM 10.3 CVIEW System Version Chart
8. 5/28/2012 5:52:36 AM 10.3 Perryville Southbound Electronic Screening Build Chart