1 / 37

INSTALLATION OF IN-PAVEMENT LIGHTS IN CONCRETE PAVEMENT & IMPACT ON LIGHT PHOTOMETRICS

INSTALLATION OF IN-PAVEMENT LIGHTS IN CONCRETE PAVEMENT & IMPACT ON LIGHT PHOTOMETRICS. Ornulv (Arnie) Sonsteby, PE & Doron Lean. Penn State / FAA Airport Conference 2007. IPRF-03-1 Project. Best Practices Guide for In-Pavement Lighting, PCC Pavement . Estimated Completion: 2007

charo
Download Presentation

INSTALLATION OF IN-PAVEMENT LIGHTS IN CONCRETE PAVEMENT & IMPACT ON LIGHT PHOTOMETRICS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSTALLATION OF IN-PAVEMENT LIGHTS IN CONCRETE PAVEMENT & IMPACT ON LIGHT PHOTOMETRICS Ornulv (Arnie) Sonsteby, PE & Doron Lean Penn State / FAA Airport Conference 2007

  2. IPRF-03-1 Project Best Practices Guide for In-Pavement Lighting, PCC Pavement Estimated Completion:2007 PI & Contact:Ornulv (Arnie) Sonsteby, P.E. email:osonsteby@burns-group.com Sponsored by:FAA, in Cooperative Agreement with Innovative Pavement Research Foundation (IPRF)

  3. GUIDE CONTENT • Coordination between disciplines • Installation in new vs. existing PCC • Products, methods, tolerances • Boxouts / blockouts • Deficiencies and corrective alternatives • Strength and load transfer

  4. Preparing Light Base & Jig

  5. Light Base Installation • “Anchor” function (preparation for paving) • (b) “Strengthening” function (completed installation)

  6. INSTALLATION ISSUES • Coordination between disciplines • Selecting: • Methods & procedures • lighting products • Pavement materials • Tolerances & verification

  7. CCOORDINATION IN DESIGN • Light location vs. pavement joints • Materials and method • QC/QA • Tolerances and Consequences

  8. PCC JOINT CONFLICTS • Touch Down Zone Lights • Lead-off / Lead-on TW CTL Lights • TW CTL Lights at curves / intersections • In-pavement RGL / Stop Bar Lights

  9. MATERIALS & METHODS • Light Base, Conduit, Pavement materials • Installation procedures and “structure” -- in new or existing pavement • Surface finish (“cookie cutter” vs. Core)

  10. QC / QA The quality of installation depends on: • Good design by engineer • Good craftsmanship by installer • Close coordination between disciplines • Inspection / verification of compliance

  11. Tolerances and Consequences • Pavement vs. Base tolerances • Light Base: Location, Height, Azimuth, Level • When to modify, when to replace

  12. Light Tolerances Location:Per AC. Depends on type and function of light. Height:Fixture edge even with pavement, (low side): +0”, -1/16. Azimuth:Within ± ½ degree. Level:With horizon. No tolerance specified. ** Paving elevation tolerance -- + ½”

  13. Level Tolerance? • Pavement has longitudinal grade & cross slope (up to 1.5% major R/Ws) • No tolerance in AC. Engineer may establish tolerance (varies) • Tolerance applied in wrong direction worsens condition • Consider 

  14. Ht D Ht D Deg Grade for 12” for 6” O 1/2 0.9% 0.1” 0.05” O 1 1.75% 0.2” 0.1” Level !! TRANSVERSE SLOPE LONGITUDINAL GRADE

  15. COORDINATION IN CONSTRUCTION • Survey • Materials and method • QC/QA • Tolerances and Consequences

  16. Survey • Coordinate survey activities • Survey to: • Locate light • Install light base • Verify before paving

  17. Selecting Materials & Methods • Submittals review for compliance • Establish installation sequence and responsibilities • Inspection --- more inspection • Protect lights while completing paving

  18. Light base Conduit in pavement base layer Setting base “in space”

  19. Setting bases in “fill-in” lane

  20. Installation in existing PCC Pavement RW Edge Light, Toe-In

  21. QC / QA • Verify light location • Verify height, azimuth & level while securing light base • Check tolerances prior to paving • Inspect surface finish • Protect light while paving, grooving, sweeping, and marking

  22. 2’ from Joint Issue • AC 150/5340-30 R/W CTL: “The line of lights is offset a maximum of 2’ from the runway centerline to the edge of fixture.” T/W CTL: “Fixtures should be installed so that their nearest edge is approximately 2’ from any rigid pavement joint.” • Modeling: (by Tigerbrain)

  23. σ - bottom of 18” thick 20’x20’ slab B-777 (254K edge loading).

  24. σ - top of 18” thick 20’x20’ slab B-727 (corner loading).

  25. Joint Issue Comments • Pavement Design is conservative (edge stress, no load transfer). • Modeling (with no load transfer between slabs, no bonding to underlying layer): • Dowels generally reduced max edge stress by ~ 20%. • With 2 dowels omitted, max edge stress reduced by ~ 12%.

  26. (Joint Issue Comments continued) • Hence: Inside 2’, with 1 or 2 dowels omitted has minimal impact on slab-slab load transfer. • Load transfer between light base and pavement – assessment suggests non-issue. • Embedded steel can help control cracking close to joint. • Alternative: Boxout

  27. PCC Joints 7” Light base 18” Light near PCC joint

  28. Details, details !! PCC Joint Cracks In-Pavement Light Conduit Kerf

  29. T/W CTL Light Boxout at PCC joint

  30. Normal joints Crack Doweled joint for Boxout Boxout at PCC joints !

  31. Threshold Light Bar “boxout”

  32. A few Related concerns

  33. KERFS PCC Joint Maintain existing pavement joints - for full section of kerf !

  34. Conduit below !! Longitudinal crack center T/W slab T/W Centerline Light

  35. Faulty sealing

  36. Fate of out-of-tolerance light bases!

  37. Doron

More Related