Eastern School Compound . Term Paper August 2005 CEM 512 Done For Dr. Saddi Assaf Done By. Mohammed Bader. Introduction. The importance of the exterior cladding in building projects has been growing in the last decades
E N D
Eastern School Compound Term Paper August 2005 CEM 512 Done For Dr. Saddi Assaf Done By. Mohammed Bader
Introduction • The importance of the exterior cladding in building projects has been growing in the last decades • The verity of exterior cladding systems is increasing due to the intensive development in this field for both nonresidential and residential buildings.
Introduction (cont..) The following factors favor this trend: • The continuous expansion in high-rise building, where the designer needs light materials • New functional demands • Rising costs of building • Increased awareness of architectural and aesthetic values
I. Information Gathering Phase The project • Four schools located in Dammam city • Total area of the terrain is around 9000 M² • The area of each school is around 1225 M² • Each school has 3 typical floors, and the height for each floor is 3.5 M • Each School has around 1890 M² cladding area
Objectives The exterior cladding must have: • Acceptable initial cost • Low maintenance cost • Weather resistant • Good look
Sources • Building Products Company (BPC), Eng :Amer Awad (Regional Manager) • GEMCO, Mr: Malek (Sales Manager) • My experience in the building materials
In this phase, many and different proposals must be created as many as possible. These proposal are as follows Proposals II. Speculation Phase
III.Evaluation Phase In this phase, a methodological process will be utilized to come up with the most suitable solution.
Methodological process • Comparison • Weighted Evaluation • Analysis Matrix
Last Ranking • ASK Board • Finished Masonry Block Wall • Granite Cladding • Cement Board
Development Phase When we clad the building with ASK board, we will get the following result; Cost=1890*130=245600 SR\building Cost of the 4 buildings = 982800 SR
Development Phase It’s the time now to develop a method which reduces the cost of the cladding.
Development Phase (cont..) A combination of two different types of cladding can be used in the project without affecting the basic function of the building, as shown in the picture.
Development Phase (cont..) Cost = (1470 M² * 130 SR) + (420 M² * 80SR) = 191100 + 33600 = 224700 SR Total Cost = 898800 SR Total Saving Percent = (982800-898800)\982800 * 100 = 8.5 %
Development Phase (cont..) • Maintenance and Painting Cost = (1470 M² * 10) + (420 M² * 5) • = 14700 + 2100 = 16800 SR \ yr \ M² • Total Maintenance Cost = 67200 SR \ yr \ M² • Total Saving Percent = (75600- 67200) / 75600 * 100 = 11.1 %