Settlement Discussion for NOIE DRG > 50kW and < 1 MW. Don Tucker & Calvin Opheim. NOIE DRG > 50kW & <1MW – Registered as Generation. Total ERCOT Generation 200 MW + .1 MW = 200.1 MW Total NOIE Load Inflow – Outflow + Internal Generation 40 MW + .1 MW = 40.1 MW Total ERCOT Load
E N D
Settlement Discussion for NOIE DRG > 50kW and < 1 MW Don Tucker & Calvin Opheim COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Registered as Generation • Total ERCOT Generation • 200 MW + .1 MW = 200.1 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 40 MW + .1 MW = 40.1 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 160 MW + 40.1 MW = 200.1 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 200.1 MW – 200.1 MW = 0 • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Treated as “load inflow” • Total ERCOT Generation • 200 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 40 MW + .1 MW = 40.1 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 160 MW + 40.1 MW = 200.1 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 200 MW – 200.1 MW = -0.1 MW • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Exemption from Reporting • Total ERCOT Generation • 200 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 40 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 160 MW + 40 MW = 200 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 200 MW – 200 MW = 0 • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Registered as Generation • Total ERCOT Generation • 200 MW + 80 MW + .1 MW = 280.1 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 0 - 40 MW + 80 MW + .1 MW = 40.1 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 240 MW + 40.1 MW = 280.1 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 280.1 MW – 280.1 MW = 0 • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Treated as “load inflow” • Total ERCOT Generation • 200 MW + 80 MW = 280 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 0.1 MW - 40 MW + 80 MW = 40.1 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 240 MW + 40.1 MW = 280.1 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 280 MW – 280.1 MW = -0.1 MW • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force
NOIE DRG > 50kW & <1MW – Exemption from Reporting • Total ERCOT Generation • 200 MW + 80 MW = 280 MW • Total NOIE Load • Inflow – Outflow + Internal Generation • 0 - 40 MW + 80 MW = 40 MW • Total ERCOT Load • Total Competitive ESI ID Load + Total NOIE Load • 240 MW + 40 MW = 280 MW • UFE • Total ERCOT Generation – Total ERCOT Load • 280 MW – 280 MW = 0 • Note: Simplified examples assume no system losses COPS NOIE DRG Settlements Task Force