1 / 23

Student Center Project

Student Center Project. Manifesting a Vibrant Learning and Campus Life Experience. History of Project. Breakthrough Project Student Initiated Committee Representation Student Input Focus Groups 6 Groups/100 Students Electronic Student Survey 735 Completed/Cross-Section of Students.

chun
Download Presentation

Student Center Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Student Center Project Manifesting a Vibrant Learning and Campus Life Experience

  2. History of Project • Breakthrough Project • Student Initiated • Committee Representation • Student Input • Focus Groups • 6 Groups/100 Students • Electronic Student Survey • 735 Completed/Cross-Section of Students

  3. Services Demand Dining & Retail

  4. Space Demand Of 48 potential spaces, demands were weighted towards six fundamental services.

  5. History of Project (Continued) • Student Senate Vote • $85.00 Per Semester • Based on Survey Data • Instituted at Semester of Groundbreaking • No Fees Collected to Date • Building Design Work • Student/Student Organizations Input

  6. Interim Actions • Extended Cafeteria Service • Extended Library Hours • Student Spaces Project • Completion of Oak Street Hall

  7. OriginalDesign • Expansion/Remodeling of University Center

  8. OriginalDesign

  9. From Challenge to Opportunity • Library Project • Student Center Funding Delay • Potential Relationship of Projects

  10. Current Proposal • Location • Use of Current University Center • Purpose • Student Center • Program Elements

  11. Campus Aerial

  12. University Center Usage • Pierson Auditorium • Meeting Rooms • Computer Lab • Potential Student Services

  13. Program Elements • Student Conveniences • One-stop Shop • Dining/Kitchen/Servery • Coffee/Cyber Café • Convenience Store • Barbershop • Other Retail • Quiet Study Lounge (Library) • Computer Lab (Library) • Parking (Library) • Meeting Spaces • Lobby/Lounge • Multipurpose Room • Small Meeting Rooms (Library) • Auditorium and Lecture Hall (Library) • Student Activities • Student Activity Venue/T.V.

  14. Program Elements, cont. • Student Government/Organizations • Student Government Chamber • Activity and Program Council • Organization Planning Space/Hoteling Spaces • Student Services • Meditation Room • Student Life Office • Disabled Student Services • Multicultural Affairs • Administrative Offices

  15. COLLECTIONS CAFE REFERENCE LEVEL ONE SCHEME B PERIODICALS/ READING ROOM INFORMATION COMMONS LECTURE HALL AUDITORIUM MEETING ROOMS ACCESS SERVICES “UNIVERSITY WAY” (51ST STREET) ACTIVITIES/ LOUNGE ENTRY CAFE FINE ARTS CENTER BOOKSTORE ONE STOP SHOP TO UNIVERSITY CENTER

  16. COLLECTIONS STAFF LEVEL TWO SCHEME B OPEN STUDY EXHIBIT CLASSROOMS/MEETING “UNIVERSITY WAY” (51ST STREET) MULTICULT ADMIN DISABLED V C ACT PROG CONF STU LIFE STU GOV LOUNGE FINE ARTS CENTER STUDENT ORGS TO UNIVERSITY CENTER

  17. COLLECTIONS LEVEL THREE SCHEME B LEARNING CENTER ACADEMIC DEV CENTER TECH SERVICES “UNIVERSITY WAY” (51ST STREET) MULTIPURPOSE SUPPORT SERVERY FINE ARTS CENTER SUPPORT DINING TO UNIVERSITY CENTER

  18. COLLECTIONS STAFF LEVEL FOUR SCHEME B WRITING CENTER SPECIAL COLLECTIONS “UNIVERSITY WAY” (51ST STREET) FINE ARTS CENTER TO UNIVERSITY CENTER

  19. Entry ENTRY

  20. Proposal Summary • Total Square Footage: 109,126 sq. ft. • Total Cost: $28,040,000.00 • Source of Funds: • Student Fees: $23,840,000.00 • Institution/Campus Funds: $3,000,000.00 • Private Development/Campus Funds: $1,200,000.00

  21. Projected Project Timeline • Design/Student Input: 2005 • Groundbreaking: Spring 2006 • Anticipated Opening: Spring 2008 • Library Opening: Late Spring 2009* *Best Case Scenario: Assumes all funding in place by FY2007

  22. Next Steps • Student/Faculty/Staff Communication/Input • Expansion of Existing Committee • Board of Curators Approval

  23. Q&A