Join Peter Johnston, CEO of Sydney Mining Club Luncheon, on Aug 1, 2002, as he discusses Murrin Murrin's performance, promises, and challenges, including issues with production, debt, and corporate governance. Learn about the joint venture, construction history, and the crucial steps needed for future success. The presentation covers the project's background, major issues, and a roadmap for debt restructuring and operational improvement. Discover insights into Murrin Murrin's current state and the strategies for a sustainable future.
E N D
Reality Bites Peter Johnston, CEO Sydney Mining Club Luncheon 1 August 2002
Agenda • Background to Murrin Murrin & Anaconda • Major issues impacting on current position • The promises • The facts (current performance) • Now and the future • Summary
Murrin Murrin Joint Venture • Murrin Murrin is a 60/40 Joint Venture between Anaconda Nickel Ltd and Glencore International AG • Project is located in the North Eastern Goldfields region of Western Australia • Design Basis: • 4 MTPA Mill Feed • 45,000 TPA Nickel (LME) • 3,000 TPA Cobalt • Current reserve approx 300 Million tonnes at 1% Nickel • Process Design based on licensed Sherritt Technology
Murrin Murrin • Project Construction started in May 1997 • US$420m Financing Aug 1997 • Mechanical Completion Dec 1999 • Lloyds Insurance Recovery (A$113m) Aug 2000 • Commercial Production April 2001 • Fluor Arbitration – 1st stage • - Begins Jan 2002 • - Interim award Sep 2002
Significant commissioning delays Slow production ramp-up Capital cost overruns True operating costs still emerging Technical viability Short term liquidity/viability Debt restructuring essential Major Issues
The promises: Three Nickel Provinces (3NP) Dominating Australia’s rich and ancient Yilgarn Craton
The promises – Production profile Announced PlansDate announced 2000 1999 1998 1997 1995 Expected
The promises – Production profile Announced PlansDate announced 2000 1999 1998 1997 1995 Expected
The promises:Corporate Governance – the missing 5th autoclave Quotes from Quarterly Reports: • Sep 99 - 100 day rolling expansion • Mar 00 - studying installation of 5th autoclave • Jun 00 - tenders received for 5th autoclave • Sep 00 - contract has been let for supply of 5th autoclave • Dec 00 - 5th autoclave specifications finalised • Mar 01 - progress on 5th autoclave continued • Jun 01 - ramp up strategy in line with forecast
Over promising – The Share Price Reality Debt restructure requirement announced
The facts: Cash burn Cashflow: 6 months July – Dec 2001 $ million
The facts: Commissioning delay Design Actual
Restructured the organisation Reduced overhead $457.4m loss for Dec 2001 half year Re-budgeted next 18 months - realistic Reduced all peripheral activities Resolved liquidity issues Debt restructuring negotiations commenced Now and the futureNew management – achievements to date
Now and the futureAbsolute imperatives • Debt restructure - Complete recapitalisation • Murrin Murrin operations – plant performance • Focus on cost management • Retention of key personnel • Eliminate legacy legal disputes • Remain cash positive pre financing • Resolve Fluor Daniel arbitration • Transparent organisation – focus on corporate governance
Summary • Debt restructure close to resolution • Murrin Murrin performance trending up • Experienced management team in place • Consolidation phase: - reduce costs - reduce production variability - generate positive cash flow • Clean balance sheet • Viable long term future