Department of Energy Electrification Indaba 15-16 March 2012 Presenter: Serutle Ntlatleng Energy Department

CITY OF EKURHULENI . Department of Energy Electrification Indaba 15-16 March 2012 Presenter: Serutle Ntlatleng Energy Department. Content. Background Service Delivery Backlogs High Level Budget Overview INEP Funding History and performance 2011/12 - Current Projects

claudia
Download Presentation

Department of Energy Electrification Indaba 15-16 March 2012 Presenter: Serutle Ntlatleng Energy Department

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CITY OF EKURHULENI Department of EnergyElectrification Indaba15-16 March 2012Presenter: Serutle NtlatlengEnergy Department

  2. Content • Background • Service Delivery Backlogs • High Level Budget Overview • INEP Funding History and performance • 2011/12 - Current Projects • 2012/13 – Proposed Projects • 2013/14 – Applications to be submitted • Challenges • Conclusion

  3. BACKGROUND • TOTAL AREA 2000 KM² • TOTAL POPULATION • STATS SA 2001 2,7 mil • PROJECTED 2010 3 mil

  4. Service Delivery Backlogs

  5. High Level Budget Overview

  6. INEP Funding History and performance • 2007-2009 – DoE not happy with EMM performance • Funded projects not completed on time • Lack of communication, process alignment and failure to report • 2009/10 – DoE withdrew funding • Intervention by other Metro’s and AMEU • Also EMM introduced new faces to electrification section • Improved communication, reporting and processes • 2010/11 – DoE made aware of existing EMM backlog • All funded projects successfully completed • More funding made available to address the huge backlog 6

  7. CURRENT PROJECT – 2011/12 More than 80% connections report by end Feb

  8. 2012/13 Proposed Projects The projects have been submitted to DoE and site inspection is schedules

  9. 2013/14 Applications 20 000 connections/annum will help reduce the backlog

  10. Challenges – Municipal Level • Finance department can only allow DORA approved projects to be initiated for implementation • The growing backlog of formal townships without access to electricity due to high rate of formalisation • The growing backlog of informal settlements due to high rate of urbanisation • The growing backlog of infrastructure maintenance and upgrading due to aging networks and demand • Illegal connections causing network failures due to overloading • High levels of theft and damage to infrastructure put pressure on already stretched resources

  11. Challenges – DoE Level • Bare minimum specification compromising the quality of service • Designs for pure overhead systems vs. underground & high-breed systems • 20Apms supply vs. 40/60Amps supply • Revenue enhancement initiatives e.g. split metering, protective boxes, etc. • Policy constraints e.g. 80% occupation, relocation of services • Electrification of informal settlement • Funding levels, both cost/conn and INEP allocation • Reporting requirements i.e. MM Signature, Social Indexes • Short notice for approved projects on DORA

  12. Conclusion • EMM had performance challenges on the INEP • Indication are that performance on INEP is improving • Good communication and reporting are key for the success of the municipality on the INEP • The municipality is faced with a huge backlog and requires special intervention from DoE • EMM is committed to work closely with DoE in eradicating the electrification backlog.

  13. THANK YOU & QUESTIONS