1 / 22

TEAM STEADY SUPPLY

ERIC VANDENBURG, SPENCER HOMAN, TREVOR LARSON and NIK URLAUB Team website: http://seniordesign.engr.uidaho.edu/2010-2011/microgrid /. TEAM STEADY SUPPLY. Table of contents:. Background Problem Definition Uninterruptible Power Supply (UPS) Current Design Design specifications

cliff
Download Presentation

TEAM STEADY SUPPLY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERIC VANDENBURG, SPENCER HOMAN, TREVOR LARSON and NIK URLAUB Team website: http://seniordesign.engr.uidaho.edu/2010-2011/microgrid/ TEAM STEADY SUPPLY

  2. Table of contents: • Background • Problem Definition • Uninterruptible Power Supply (UPS) • Current Design • Design specifications • Load information • Proposed Design # 1 • Constraints • Proposed Design # 2 • Proposed Design # 3 • Ideas • Design Tradeoffs • Budget • Schedule

  3. Background: • Advanced Electric Ship Demonstrator (AESD) also known as “Sea Jet” • 1/4 scale model, Length: 133 feet, Weight: 239,000 lbs, Location: Bayview, Idaho • AESD is used for a variety of different tests and experiments (eg. Acoustic data collection, Hull modification, Motor types) • Propulsion System is powered by 720 12V@40A/Hr Batteries • Auxiliary System is powered by 4 UPS • Shore power, Diesel Engine used for charging

  4. Problem Definition: • This is a Feasibility Study with the following objectives: • Replace the Four Uninterrupted Power Supplies (UPS) • Provide Uninterrupted Power Flow to Every Auxiliary Load. • Increase the Duration of Battery Run Time (Increase Quiet Mode Run time) • Decrease Charge Time for Batteries (Decrease Time Between Quiet Mode Runs) • Decrease Acoustic Contamination

  5. What is an uninterruptible power supply (UPS): • PROS • UPS provide a Load with power at all times • During connection to Shore/Diesel Generator, Load is powered and battery is charging. • During Quiet Mode Runs the Battery supplies the Load with power • CONS • UPS are not designed to run on the internal batteries for extended time • UPS are not designed to charge quickly • UPS are not designed to minimize acoustics (Inverters) • 4 UPS = 4 Inverters = Loud SHORT QUIET MODE RUNS LONG CHARGE TIME ACOUSTIC CONTAMINATION

  6. Current Design:

  7. Design specifications: • Continuous power supply to the loads at all times. • Draw power from a common bus. • Batteries capable of providing power for more than 45 minutes. • Remove the (4) uninterruptible power supplies (UPS) causing unwanted acoustics

  8. Design process: • Brainstormed/researched DC microgrids • Obtained load profiles from NAVSEA • Calculated power consumed by the auxiliary power system • Determined the number of batteries needed. • Would it be feasible to run auxiliary loads off of the propulsion system.

  9. Load information: With Onboard Data Acquisition System (ODAS) equipment off: • UPS #1 – 6.0A • UPS #2 – 13.9A • UPS #3 – 2.0A • UPS #4 – 3.3A With ODAS equipment on: • UPS #1 – 17.4A • UPS #2 – 18.5A • UPS #3 – 7.3A • UPS #4 – 3.3A UPS #4 has weak batteries causing ODAS configuration not to be utilized for this unit.

  10. Design Schematic# 1 Estimated run time: 46.997 minutes

  11. Design #1 Calculations

  12. Constraints: • Space: Current UPS dimensions 4*(4ft. by 2ft. by 2ft.). Battery dimensions 24*(12 in. by 6 in. by 4 in.) SPACE not a problem. • Cost: Compare each design (Comparison in tradeoff Table)

  13. Design Schematic # 2 • Auxiliary System ties into one battery string of the Propulsion System • Auxiliary load is roughly only 12% of Propulsion load. Propulsion System will be able to support auxiliary system. • Vital Loads have power at all times • Estimated run time: • 1 Hour 45 minutes

  14. Design #2 Calculations

  15. Design Schematic # 3 • Auxiliary System ties into all 6 battery strings of the Propulsion System • Auxiliary load is roughly only 1% of Propulsion load. Propulsion System will be able to support auxiliary system. • Vital Loads have power at all times • Estimated run time: • 21.399 Hours

  16. Design # 3 Calculations

  17. Options Considered • Current Lead-Acid Batteries (12V @ 40A/Hr) • Lithium-Ion Batteries (36.8V @ 50A/Hr) • Fuel cells (not feasible) • Size needed for storage • cost • Back up battery bank for Design # 2 • Types of Inverters, most cost effective and easy to implement

  18. Design Tradeoffs

  19. Project Learning • Gained knowledge of DC microgrids • A better understanding of one-line diagrams • Basic battery bank design • Better team communication • Site visit • The operations and uses of the AESD

  20. Budget: • Site Visit (2): $308.80 • Poster: $75.00 • Total: $383.80

  21. Schedule: • Start of Semester: January 10, 2011 • Detailed Design Review: February 15,2011 • Snapshot Day: March 8, 2011 • Expo: April 29, 2011 • Logbooks Due: May 5, 2011 • Final Report: May 5, 2011

  22. Questions:

More Related