An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Keystone Center Joint Fact-Finding On Nuclear Power

  2. Endorsements This report is designed to be an accurate portrayal of the NJFF group’s discussions and joint findings. By endorsing this report, participants agree that they “generally support” the package of findings and the way the issues are described. To ensure an open and candid dialogue, participants presented their personal opinions in the Dialogue deliberations and not necessarily the official positions of their organizations. Therefore, the recommendations do not represent official government or organizational positions. *Peter Bradford, Bradford Brook Associates Former NRC Commissioner David Brown Exelon Mark Brownstein Environmental Defense *Thomas Cochran Natural Resources Defense Council *Armond Cohen Clean Air Task Force *Paul Genoa Nuclear Energy Institute Victor Gilinsky Energy consultant Former NRC Commissioner Chris Maslak GE Energy – Nuclear *Patrick Mazza Climate Solutions *Brian Moline Kansas Corporation Commission *Mano Nazar American Electric Power Brian O’Connell NARUC Timothy Pettit Duke Energy *Sonny Popowsky Pennsylvania Office of Consumer Advocate Vito Stagliano National Commission on Energy Policy Jonathan Temple British Embassy Steve Ward Maine DEP, Former Public Advocate, Maine’s Public Advocate Greg White Michigan PSC Michael Wilson FPL Group Kurt Zwally National Wildlife Federation *Steering Committee Mike Godfrey Southern Nuclear Judi Greenwald Pew Center on Global Climate Change James Harding Consultant, Formerly Seattle City Light Randy Hutchinson Entergy Corporation William Lanouette Writer and public-policy analyst Allison Macfarlane George Mason University *Ted Marston Marston Consulting Nuclear Power Joint Fact-Finding Catherine Morris, The Keystone Center

  3. Key Findings • There was no agreement on the likely expansion of nuclear power. To achieve 25 gigatons of carbon reductions over 50 years would require sustaining the most rapid decade of historical growth in nuclear power for that entire period. • The estimated life-cycle cost of electricity from new nuclear plants might reasonably be between 8 to 11 cents per kWh based on recent construction experience and escalation of construction materials. • Safety and security has improved in the U.S. The safety and security culture in some countries raises concerns about further expansion of nuclear power abroad. Nuclear Power Joint Fact-Finding Catherine Morris, The Keystone Center

  4. Key Findings • Geologic repositories are the best option for long-term disposal of spent fuel. Given our experience with Yucca Mountain, the search for a second or alternate site would benefit from a different approach. • Older spent fuel can be stored safely and securely on-site. Centralized facilities are a reasonable option for spent fuel from decommissioned plants. • Diversion or theft of material from bulk fuel handling facilities is a principle proliferation concern. • GNEP attempts to address several proliferation concerns over expanding nuclear power globally, but the program is not a credible strategy to solve the radioactive waste problem or the proliferation problem. Nuclear Power Joint Fact-Finding Catherine Morris, The Keystone Center

  5. Climate Change: Major Reason for Study • Under “business as usual” projections, global CO2 emissions from fossil fuels are expected to double by 2050 – from 7 GtC/yr to 14 GtC/yr. • But stabilizing the atmosphere at 500 PPM CO2 requires avoiding this growth and then rapidly shrinking CO2 emissions after 2050. • To get to 2050, we would need seven “wedges” of low-carbon energy, each enough to displace 25 GtC over 50 years. Source: Pacala, Socolow. Carbon Mitigation Initiative. Princeton U. Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  6. How much nuclear capacity would that mean? One wedge would require that we roughly triple the size of global nuclear power plant capacity, from 370 GW to 1070 GW, or about 700 net GW. Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  7. To sustain a wedge, first we would need to replace most existing plants over 50 years Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  8. Build Rate for a Wedge 1070 GW would mean an average build rate of approximately 20 GW per year for 50 years, comparable to the rate achieved during the fastest ten-year period of world nuclear expansion (1981-90). Historic nuclear build rate by decade (MW) 20 GW/yr Source: IAEA data Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  9. How does this compare to current projections? • More optimistic than current announcements reported by WNA for new plants • Higher than average 40-year historical growth rate • More rapid than rate forecast by DOE for U.S. Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  10. Additional infrastructure needed to support one nuclear wedge • 11-22 large enrichment plants • 18 fuel fabrication plants • 10 nuclear waste repositories the size of the statutory capacity of Yucca Mountain—713,000 tons of spent fuel. Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  11. Effect of Climate Change Policy • In a carbon-constrained world, in which either a substantial greenhouse gas (GHG) tax or cap and trade program is implemented, the relative economics of nuclear power (as compared to fossil-fueled power) will improve. • The degree of relative improvement will depend on such factors as the stringency of the carbon cap and the means of allocating carbon allowances. Nuclear Power Joint Fact-Finding Armond Cohen, Clean Air Task Force

  12. Regulatory Framework While some companies have announced their intentions to build “merchant” nuclear power plants, it will be easier to finance nuclear power in states where the costs are included in rate base with a regulated return on equity. Status of State Electric Industry Restructuring Activity As of February 2003 Source: EIA Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  13. Levelized Life Cycle Cost A reasonable range for the expected life cycle cost of new nuclear power is between 8 and 11 cents per kWh delivered to the grid. Summary of Life Cycle Cost (Cents/kWh) Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  14. Cost Analysis Assumptions Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  15. This Is Today’s Picture General Construction Cost Indices Source: Chemical Engineering Magazine, August 2006 Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  16. Fuel Cost Issues Source: Thomas L. Neff, Center for International Studies, MIT, “Uranium and Enrichment Supply”; Presentation Winter 2006 Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  17. Scale-Up Issues • More standardized design and better construction practices • But, there’s been a loss of US industrial capacity: • Skilled labor and materials issues • Only two steel mills worldwide available for forging large components • Six year lead-time for other key components • Reduced number of sub-suppliers; N-Stamp Holders • Other pinch points throughout the supply chain, with potential for monopoly pricing • Fragmented market structure – different utilities; different contractors • Uranium mining and enrichment capacity Nuclear Power Joint Fact-Finding Jim Harding, Energy Consultant

  18. Safety and Security • On balance, most commercial nuclear power plants in the U.S. are safer today than they were before the 1979 accident at Three Mile Island. • Concerns about nuclear plant expansion in certain other countries that currently have significant weaknesses in legal structure (rule of law); construction practice; operating, safety, and security cultures; and regulatory oversight. While plants have gotten safer since the TMI accident, public concern over plant security is greater today than it was before September 11, 2001. Transparency is a key cornerstone for public trust-building. Over the next 2 or 3 decades, the safety and security of the U.S. nuclear industry will largely be determined by that of existing reactors. Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  19. Safety and Security Substantial changes have been made to the nuclear power plant licensing process in the last 15 years.  Some members of the group believe that the procedural modifications limit effective public involvement and could have a deleterious effect on safety and security. Old 10 CFR Part 50 Licensing Process New NRC 10 CFR Part 52 Licensing Process Limited Work Authorization* Early Site Permit * Construction Permit Application * Combined License * Construction Construction Operating License Application* Construction Acceptance Criteria Met * Design Certification * Operating License Issued * Operations Operation * Public Comment Opportunity Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  20. Waste Spent nuclear fuel must ultimately be placed in long-term disposal facilities, and the best disposal option is a deep underground geologic repository. Schematic of a typical nuclear waste repository Source: http://www.dalton.manchester.ac.uk/research/areas/geotechnical/images/Repository_001.jpg Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  21. Waste • Yucca Mountain has a statutory capacity limit that is less than the amount of spent fuel expected to be produced by currently operating reactors over their licensed lifetimes. • The Yucca Mountain project has repeatedly failed to meet its own schedule. Given this experience, the search for a second site or an alternative site would benefit from a different approach. Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  22. Waste Older spent fuel must be stored on an interim basis until an operating repository is available. This spent fuel can be stored safely and securely in either spent fuel pools or dry casks, on-site. Centralized interim storage is a reasonable alternative for managing waste from decommissioned plant sites and could become cost-effective for operating reactors in the future. Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  23. Waste Transport of spent fuel and other high-level radioactive waste is highly regulated, and it has been safely shipped in the past. Transport of spent fuel to any repository will take many years to complete, and will require ongoing regulatory oversight and continued vigilance. Nuclear Power Joint Fact-Finding Paul Genoa, Nuclear Energy Institute

  24. Reprocessing • While reprocessing of commercial spent fuel has been pursued for several decades in Europe, overall fuel cycle economics have not supported a change in the U.S. from a “once-through” fuel cycle. • The long-term availability of uranium at reasonable cost suggests that reprocessing of spent fuel will not be cost-effective in the foreseeable future. • A closed fuel cycle with any type of separations program will still require a geologic repository for long term management of waste streams. Source: NJFF calculations based on the same approach used in MIT study. Nuclear Power Joint Fact-Finding Tom Cochran, Natural Resources Defense Council

  25. Proliferation • Expansion of nuclear power in ways that substantially increase the likelihood of the spread of nuclear weapons is not acceptable. • Critical shortcomings in current IAEA safeguards and the international community has not demonstrated that the enforcement mechanisms are effective. • A principal proliferation concern is the diversion or theft of material from bulk fuel handling facilities (e.g., reprocessing, enrichment, mixed oxide fuel fabrication, and plutonium storage facilities) to develop weapons capability. Nuclear Power Joint Fact-Finding Tom Cochran, Natural Resources Defense Council

  26. Proliferation Growing stocks (250MT and growing at 10 MT/yr) of civilian separated plutonium pose a significant proliferation risk and require extraordinary protection and international attention. Diversion or theft of these stocks represents a risk of weapons development by sub-national terrorist organizations. Levels of physical protection and risk vary widely from country to country. Estimated Quantities of Civilian Separated Plutonium by Country Nuclear Power Joint Fact-Finding Tom Cochran, Natural Resources Defense Council

  27. Global Nuclear Energy Partnership • Group agrees with several premises of the GNEP, but the program is not a strategy for resolving either the radioactive waste problem or the weapons proliferation problem. GNEP attempts to address the following proliferation concerns: • All grades of plutonium, regardless of the source, could be used to make nuclear explosives and must be controlled. • Reprocessing poses a problem in non-weapons states. Widespread use of mixed-oxide fuel by both weapons states and non-weapons states is similarly troublesome. • Even in the weapons states, plutonium must be protected, and one should not increase stocks of plutonium in separated or easily separated forms such as mixed-oxide fuel. Nuclear Power Joint Fact-Finding Tom Cochran, Natural Resources Defense Council

  28. Global Nuclear Energy Partnership • The participants believe that critical elements of the GNEP are unlikely to succeed because it requires: • Deployment of commercial-scale reprocessing plants, uneconomical to date. • A large fraction of commercial reactor fleets to be fast reactors, but to date have proven to be uneconomical and less reliable than conventional LWRs. Source: http://www.gnep.energy.gov/gnepProgram.html Nuclear Power Joint Fact-Finding Tom Cochran, Natural Resources Defense Council

  29. For More Information • Full text available at www.keystone.org • Catherine Morris, Director Energy Program (202) 452-0785, cmorris@keystone.org Nuclear Power Joint Fact-Finding