AIRSPACE CONCEPT WORKSHOP CASE STUDY. BEIJING, CHINA; 30 JUN-11 JUL 2014. PBN Implementation Processes. Airspace Concept Activity Overview. XIAN Info. XIAN Info. XIAN Info. XIAN Info. XIAN Info RWY23R. XIAN Info RWY23L. XIAN Info RWY05R. XIAN Info RWY05L. XIAN Info. XIAN Info.
E N D
AIRSPACE CONCEPT WORKSHOP CASE STUDY BEIJING, CHINA; 30 JUN-11 JUL 2014
XIAN Info • Area Controls: open 24/7 • Terminal Approach Radar operational: 24/7 • Radar: • Xian: Rwys 05L/R and 23L/R • ILS CAT II RWY23R • Approx 67 arrivals per day
XIAN Info • More than 90% of operators RNAV1/RNP1 qualified • APP vectors many aircraft • Military airspace has not been able to be used
YAV RWY05 LOVRA NUGLA TEBIB HO MIZ NSH
YAV RWY23 LOVRA NUGLA TEBIB HO 0 15 30 45 60 MIZ Nautical miles NSH
0 15 30 45 60 Nautical miles NSH
Rules of Thumb • CDO descent rough starting points: • 3 miles per thousand feet plus 1 mile per 10knots • or • 4 miles per thousand feet • CCO climb rough starting points: • Very Slow climber - 5 miles per thousand feet • Medium climber – 3 to 4 miles per thousand feet • Faster climber – 2 miles per thousand feet • Rocket ship - 1 mile per thousand feet • RNAV Final between 4-5 nm • Curved RNAV? A-RNP - RF prior to FAF?
XIAN • Team Organizer • Team Recorder • Team Name
XIAN 1 - Agree on Operational Requirements • Safety • Capacity • Efficiency • Environment • Access