Update on Tevatron startup activities on September 4, 2009. Cryo system status, tunnel work progress, and beam preparation details provided. Includes issues with cryo system and cold cathodes, as well as upcoming tasks and readiness for startup.

coffmanj
Download Presentation

Tevatron Startup Activities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tevatron Startup Activities September 4, 2009

  2. Cryo Status • All houses at LN2 tempsexcept D1 and E1 (room temp). • E1 and D1 are signed off for cooldown. • CHL has full load of helium. • Cryo system has been fighting hydrocarbon contamination problems in E, F and A sectors (Pbar too). • Serious controls issue where all cold cathodes in a house may read nearly equal good values.

  3. Tunnel Work • Tunnel work is mostly complete. • F-sector Electrical walkthroughs done Thursday. • Rest of Walkthroughs will be done soon. • Stacking D0 shielding blocks Tuesday. • Lowpot looks good – Hipot when full of liquid helium.

  4. Beam Preparation • DFG file will be only slightly modified from last store. • New Automatic Injection closure aggregate will probably be ready for startup. • Startup activities should consist of just general tune up and measurements. • Seperator turn on and conditioning progressing.