90 likes | 183 Views
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX 3/22/10 Update. MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX. Project Status Building #1 & Building #2 Out for Bids OSC Review and Approval for Advertisement Project Labor Agreement [PLA] has been negotiated
E N D
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX • Project Status • Building #1 & Building #2 Out for Bids • OSC Review and Approval for Advertisement • Project Labor Agreement [PLA] has been negotiated • Additional Testing of Underground Storage Tanks [UST] complete – remediation plan formulating • DEP Review of Remediation – in Progress • Police Relocation Complete
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX • Project Schedule • Advertise for Bid issued March 19, 2010 • NJ OSC approval received. • Bids Due April 16, 2010 • Anticipated Notice To Proceed (NTP) – End of April or Early May 2010 • Anticipated Project Completion November 2011
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX • Schedule Issues • DEP Review of Remedial Work • Expanded Work Area • Site Remediation • Garage – Detention Pond • UST removal adjacent to Building #1
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX • Budget • Total Budget $15 Million • Pro-active Approach To Mitigate Budget Issues • Value Engineering – Workshop conducted (3/5/10) • Identified savings and ‘bid alternates’ with out sacrificing the project program • Inclusion of Alternates – Options for consideration • Meetings on – going for ‘alternate’ funding sources • Seeking Energy Cost Rebates • Stimulus Funds Sought
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX • Budget Concerns • Unbudgeted/Under-budgeted Costs • Contaminated Soil Remediation • Storm Water Management • Police Relocation • Building Utility Separation • Renovation Challenges
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Next Steps: • Await Bid Openning on April 16, 2010 • Track Contaminated Soil Remediation Plan • Cost and Schedule Impact to be evaluated • Furniture Procurement • State Contract – Meeting 3/24/10
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX QUESTIONS