370 likes | 562 Views
The Reactor Oversight Process: Development and Results. Tom Houghton Nuclear Energy Institute September 20, 2005. What is NEI?. The Nuclear Energy Institute is the industry’s policy organization, whose mission is to foster the beneficial uses of nuclear technology in its myriad forms
E N D
The Reactor Oversight Process:Development and Results Tom Houghton Nuclear Energy Institute September 20, 2005
What is NEI? • The Nuclear Energy Institute is the industry’s policy organization, whose mission is to foster the beneficial uses of nuclear technology in its myriad forms • NEI’s membership includes 250 corporate members in 14 nations • NEI and its predecessor organizations have served the nuclear industry since 1953 • NEI’s key organizations are • Governmental Affairs • Communications • Nuclear Generation
In April 2000 NRC implemented the new Reactor Oversight Process • The new process revised, and for the first time, integrated NRC’s inspection, assessment and enforcement programs • This presentation will describe • Reasons for the change • Results to date
Industry Performance improved dramatically in the 1980s • Safety • Production (capacity factor) • Cost ($/kw)
US Electricity Production Cost Estimates (1981-2000)(in constant 2000 cents/kWh) Source: Pre 1995: UDI, Post 1995: RDI Modeled Production Cost
Industry’s safety performance, as measured by NRC and WANO indicators, continued to improve
Significant Events: Industry Average (1985-2000) Source: NUS
Safety System Performance Source: WANO 2001 Performance Indicators
Industrial Accident Safety Rate US Manufacturing IASR US Finance, Insurance, Real Estate IASR US Nuclear IASR* #Number of accidents resulting in lost work, restricted work, or fatalities per 200,000 worker hours *Full- time, on- site employees Sources: WANO and BLS
Despite objective evidence of improving safety, NRC Violations continued to increase
Increase was driven by a 100% jump in Level IV Violations (minor process and procedure errors)
The consequences of the old approach were significant, both economically… …AND in diverting NRC and industry resources from focusing on more risk significant areas
NRC agreed a new approach was appropriate • NRC’s internal reviews found the previous approach inefficient, untimely, very subjective and inscrutable to licensees and the public • Advances in risk assessment provided confidence that risk-informed performance indicators and simplified risk analyses could be used as effective assessment tools
Regulatory Oversight ProcessRisk-Informed, Performance-Based Assessment, Inspection and Enforcement Regulatory Oversight Model Licensee Provides Self Assessment & Audit Plans* Licensee Provides Self Assessments & Audit Results* Develop Inspection Plan Conduct Inspections Assess Results Determine Regulatory Action Licensee Assesses & Corrects Deficiencies Licensee Provides Safety Performance Indicators * Future
What are appropriate roles for Licensees and Regulators? Performance Model for Successful Plant Operations Inputs Management Actions Outputs People Safety Performance HumanPerformance Plant SelfAssessment CorrectiveAction Processes Cost Effective Production Procedures
Reactor Oversight Process • Public Meetings • Press Releases • NRC WebSite • PDR/ADAMS • Assessment Reports • Inspection Plans • Inspection Findings • Performance Indicators Communications Agency Response Management Conference Monitor Licensee Actions NRC Inspections Additional Regulatory Actions Assessment Process (Action Matrix) Enforcement Cornerstones of Safety Significance Evaluations Significance Evaluations Significance Determination Process Performance Indicator Thresholds Supplemental Inspections Event Response (SI/AIT/IIT) Generic Safety Inspections Risk Informed Baseline Inspections Performance Indicators Inspections Performance Indicators
Performance BandsSAMPLE INDICATOR Licensee Response Increased Regulator Response Required Regulator Response Unacceptable Performance
ACTION MATRIX INCREASING SAFETY SIGNIFICANCE One or Two inputs White (in different cornerstones) in a Strategic Performance Area; Cornerstone objectives fully met Repetitive/multiple degraded cornerstones, Multiple Y or 1R input; Cornerstone met-longstanding issues or signif safety margin reduction One Degraded Cornerstone (2 W or 1 Y input) or any 3 W inputs in strategic performance area; Cornerstones met-minimal reduction in safety margin All Assessment Inputs (PIs and Inspection Areas) Green; Cornerstone objectives fully met Overall Unacceptable Performance; Operation not permitted. Unacceptable safety margin. RESULTS Management Meeting Routine Resident Inspector Interaction SRI/BC Meet with Licensee DD/RA Meet with Licensee Management EDO (or Commission) Meet with Senior License Management Commission Meeting with Senior Licensee Management Licensee Action Licensee Corrective Action Licensee Corrective Action with NRC Oversight Licensee Self Assessment with NRC Oversight Licensee Performance Improvement Plan with NRC Oversight Baseline and Team Insp. Focused on Cause of Overall Degradation NRC Inspection Risk-Informed Baseline Inspection Program Inspection Followup Baseline and Inspection Focused on Cause of Degradation RESPONSE -10 CFR 2.204 DFI -10 CFR 50.54(f) Letter -CAL/Order Regulatory Actions None -Document Response to Degrading Area in Inspection Report Docket Response to Degrading Condition Order to Modify, Suspend or Revoke Licensed Activities Assessment Report DD review/sign Assessment Report (w/ inspection plan) DD review/sign Assessment Report (w/ inspection plan) RA review/sign Assessment Report (w/ inspection plan) RA review/sign Assessment Report (w/ inspection plan) COMMUNICATION Public Assessment Meeting SRI or Branch Chief Meet with Licensee SRI or Branch Chief Meet with Licensee RA Discuss Performance with Licensee Commission Meeting with Senior Licensee Management EDO (or Commission) Discuss Performance with Senior Licensee Management Regional Review Only Headquarters Review
Industry Actions • Developing crosscutting criteria • Performance indicators • MSPI • Replacement for Scrams w/ loss of normal heat removal PI • Alternate RCS leakage PI • Significance Determination Process (SDP) improvements
ROP continues to evolve • Availability of data has enhanced public confidence • Continue to modify performance indicators and significance determination process for inspections • Focuses industry ®ulator on risk significant issues • Degrading performance can be identified before serious increase in risk to public • Has resulted in performance improvements by focusing on problem areas • Has demonstrated need to reassess deterministic regulations • HOWEVER, ROP is not a substitute for vigilance, and a willingness to aggressively pursue off normal conditions