IBL UpdateH. Pernegger, G. Darbo(PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings
Management board • IBL Management Board • Membership: • IBL PL + IBL TC • 2 coordinators from each WG • Plus “extra” members • Module WG • (2 coordinators) • FE-I4 • Sensors • Bump-Bonding • Modules • HDI • Test & QC • Irradiation • Stave WG • (1 Phys + 1 Eng.) • Staves • Loaded Stave • Internal Services • Test & QC • Cooling Design & Stave Thermal management • IBL Integr.-Install. • (2 Eng.) • Stave Integration • Global Sup. • Beam Pipe (BP) • Ext.services inst. • IBL+BP Installation • Cooling Plant • Test & QC • Off-detector • (1 Phys + 1 E.Eng.) • Power • DCS • ROD • Opto-link • Ext.serv.design/proc • Test Beam • System Test
IBL MB Composition • PL and TC propose the following IBL (MB) Composition: • IBL Project Leader: G. Darbo (Genova) • IBL Technical Coordinator: H. Pernegger (Cern) • “Module” WG: Maurice Garcia-Sciveres (LBNL) + Fabian Hugging (Bonn) • “Stave” Working Group: Ole Rohne (Oslo) + Danilo Giugni (Milano) • “IBL Assembly & Installation” WG: Neal Hartman (LBNL) + Raphael Vuillermet (Cern) • “Off-detector” WG: Tobias Flick (Wuppertal) + Stephane Debieux (Geneva, tbc) “Extra” members: • Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), Pixel Chair (C. Gößling) • Offline “liaison”: Pixel Off-line coordinator (A. Andreazza) • TDR editor (K. Einsweiler + M. Capeans) • Working Group coordinators have been selected in discussion with IBL PL, IBL TC , the candidates and responsible of their home institutes. • Normally WG coordinators are endorsed by Institute Board • We propose to appoint WG coordinators today ad interim and present this proposal for endorsement at the IB kick-off meeting on July 8. • Appointment is for a two years term
Institute Board July 8 (Atlas week)
Working group mandate • WG coordinators will • In design phase: follow interfaces, define tasks, deliverables, study design options and contribute “their” sections to the TDR • In production phase: lead qualification process on prototypes and follow construction deliverables and tasks through the project • Track actions in their area and report them to the MB • PL and TC have asked workgroup coordinators now to prepare a “mandate” for each working group which includes: • List of activities for each WG • Update of list of deliverables where applicable • First preliminary estimate of resource needs (manpower!) and schedule for R&D, prototyping and construction • Have already a first draft for 3 WG (see last two MB meetings) • This is to be included into the IBL Project Organization Document ATU-ORG-MG-0001 by Giovanni, Heinz, Nigel ready for presentation at the IB kick-off meeting
Towards a Schedule: general consideration • Assume an installation date of Oct 2013 (obviously we will get more info during the time to come) • The schedule is build by working “backwards” from the installation date • A later date (2014?) may give us more time for RD (FEI4) but needs to be balanced with the need for contingency. • We need to forsee time for commissioning after the installation date. • The IBL is small in “number of modules” • Many components are produced with a “single batch” hence our scope to overlap activities and component production is limited • This is a first attempt with many assumptions and over the next week(s) we will develop a detailed schedule for each working area • This can then become a first “baseline” schedule • It does not yet include most of the prototyping (except on chips & sensors) • Based on this first baseline schedule we need to agree on milestones • The schedule will (in some cases) drive the decision making process and timescale for technical decisions (see later)
FEI4 drives the schedule for modules • getting the next FEI4 asap is crucial for module qualification • do we need 2 eng. Runs or 2 eng runs + 1 prod run? Stave 0 plays a crucial to qualify the IBL system (staves and off detector electronics) Service installation happens in shutdowns - need definition & procurement of services (USA15->PP2) early on to use shutdown time efficiently
Decision items • Goal is to establish • Where do we need studies? • When do we have to decide between options? • Need to understand which items need redesign and to develop a complete system layout. This can then be used to update list of deliverables and coordinate the institute’s contributions and provide input to funding requests. • The following list is sorted by working area and nothing more than a personal view • Module • Sensor technology to be used in IBL (mid 2010) • FEI4 functionality & “IBL” version: based on next prototype and its test results: this drives the schedule for IBL , need to investigate if we can build IBL on 2 engineering runs (present schedule) or need 2 eng. Runs + 1 production run (during module assembly) • Module size (end 2009?) : this drives mech. designs • Bump bonding : only 1 vendor or qualify second for FEI4? • Stave • Stave cooling : which type of pipe and coolant? (end 2009?) • Single stave or bi-stave engineering • Fittings/connectors at end of stave or “7m” object? (end 2009) • EoS card: is it passive or does it need active parts (data, power) (end 2009)
Decision items cont. • Integration and installation • Beam pipe removal feasibility study to be concluded (mid 2008) for tooling design • Exact beam pipe specs for IBL and replacement beam pipe (when?) • Support “strategy” for IBL: on BP or on a “mini” PST (when?) • Off-detector • Powering: study for what to do if DC-DC conv. nn FEI4 cannot be used (can start now) • Services inventory and detailed specifications for power,readout,cooling (end 2009?): needed to plan installation and routing • ROD/BOC specs revisited with FEI4 test results (mid 2009?)
Meetings & Work spaces • Regular meetings • Management board weekly Mo 15h30-17h30 • Module & Off-detector WG bi-weekly Thursday • Stave and Integration/Installation WG bi-weekly Tuesday • Still investigation best possible meeting configuration in ID with Pippa • General meetings : 2 days (next June 25-26) • Currently book rooms for those meetings with help from Atlas secretariat • Mailing Lists • Created one per WG + general + Management board • Share point: Collaborative work space for WGs and MB • https://espace.cern.ch/atlas-ibl/default.aspx • Action list on Share point created • “Track Issue” in MB Share Point • EDMS tree created for technical documentation • https://edms.cern.ch/cedar/plsql/navigation.tree?p_top_id=1502214928&p_top_type=P