1 / 6

12/17/09 – SEM Update

12/17/09 – SEM Update. Woody Rickerson Manager ERCOT Network Modeling. History ERCOT Network Operations Model. 2000 – June 2009. June 2009 – Sep 2009. Sep 2009 –Nodal Go-live. Nodal Go-live. SEM. Nodal Model. Nodal Model. Nodal Model. NOMCRs. SRs. NOMCRs. ERCOT. NOMCRs.

tlawless
Download Presentation

12/17/09 – SEM Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12/17/09 – SEM Update Woody Rickerson Manager ERCOT Network Modeling

  2. History ERCOT Network Operations Model 2000 – June 2009 June 2009 – Sep 2009 Sep 2009 –Nodal Go-live Nodal Go-live SEM Nodal Model Nodal Model Nodal Model NOMCRs SRs NOMCRs ERCOT NOMCRs Zonal Model Zonal Model ERCOT ERCOT SRs SRs ERCOT Zonal Model TSPs TSPs TSPs TSPs TODAY

  3. Since the Start of SEM . . . 150,160 Data and data attribute changes including: Additions to the Model (50,881) 297 breakers 3296 bays 62 power transformers 226 electrical buses 30 substations 178 lines Modifications to the Model (76,158) Deletions from the Model (23,121)

  4. SEM Issues • Owner/Operator Difficulty • Modification to allow Operator rights to create new equipment is scheduled • NPRR to clarify responsibility for modeling transmission equipment owned by non-registered entities has been written. • Large Number of Line renames • Complications with the scheduled outages • One line drawings must be updated • Contingencies must be renamed • Resource Owned Transmission Equipment • TSP naming doesn’t always match names in RARF • Database Load Frequency • Approval to Energize Process

  5. TSP Model Change Activity during SEM 1894 total submits on 11/10 1634 total submits on 10/20

  6. NDSWG Coordination • Bi-monthly Webex meetings • One-off special meetings for outstanding issues • Issue tracking worksheet • Modeling issues • Modeling guide revisions • Development of Modeling Templates • NOMCRhelp@ercot.com for immediate problems (answered almost 200 of these since SEM go-live) QUESTIONS

More Related