Search Coil Magnetometer (SCM) MCDR Alain Roux, CETP-Velizy Co-i: O.Le Contel

Search Coil Magnetometer (SCM) MCDR Alain Roux, CETP-Velizy Co-i: O.Le Contel Technical Manager: B.de la Porte* =>C.Coillot Lead Engineer: A.Bouabdellah Technicians: D.Alison & S.Ruocco *Till june 2004. Team re-organisation. Technical Manager: Bertrand de la Porte

collin
Download Presentation

Search Coil Magnetometer (SCM) MCDR Alain Roux, CETP-Velizy Co-i: O.Le Contel

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Search Coil Magnetometer (SCM) MCDR Alain Roux, CETP-Velizy Co-i: O.Le Contel Technical Manager: B.de la Porte* =>C.Coillot Lead Engineer: A.Bouabdellah Technicians: D.Alison & S.Ruocco *Till june 2004

  2. Team re-organisation • Technical Manager: Bertrand de la Porte • team management, general schedule • Lead engineer: Christophe Coillot • SCM support: design, manufacturing: • Sensors : design, manufacturing, tests, • PA: electrical design, tests procedures, EM&FM tests. • Sniffer design, manufact. & tests • Engineer: Abdel Bouabdellah • ICD&PAIP management, Vibration tests, • PA: PCB cabling, design of housing, • manufacturing, PA I/F. • Technician: Dominique Alison • PA/PCB design, • Manufacturing sensors, • I/F PA: design, manufact., tests • Technician: Sébastien Ruocco • Sniffer & tests: • Technical Manager: Christophe Coillot • team management, schedule. • SCM support: manufacturing, schedule, • Sensors : manufacturing, EM&FM tests, • PA: tests procedures, EM&FM AIT • Lead Engineer: Abdel Bouabdellah • ICD&PAIP management, Vibration tests, • PA: PCB cabling, manufacturing, PA I/F general schedule. Integrations. • Technician: Dominique Alison • PA/PCB design, • Manufacturing sensors, • EM&FM tests&integrations • Technician: Sébastien Ruocco • PA: FM tests. • Sensors: FM tests. • Integrations

  3. Sensor requirements

  4. SensibilityEM (pT/sqrt(Hz) 10 1 0.1 0.01 0.001 1 10 100 1000 10000 Fréquency (Hz)

  5. 3-axis structure Design includes EPR remarks and numerical simulation results. Interface is completely defined (cf. P. Turin). EM structure delivered by GdTech to CETP: May 17th.

  6. PA Design by 3D+ • Mechanical characteristics: • 2 amplification levels • 3 radiation shielding levels • Dimensions: 20 x 20 x 15 (mm) • Weight : 15 g Pre-Amplifier module

  7. PA Layout on PCB&box a

  8. Power &mass summary

  9. Operations • When ON, SCM is continuously measuring the magnetic field up to 4 kHz. • Once per orbit a calibration is run for 30 secs (default) • After 60 seconds, the Calibration is automatically turned off.

  10. Test Matrix

  11. Test plans : SC

  12. Test plans: PA cubes * Takes into account changes suggested during CDR peer review

  13. Test plans: full PA box

  14. Bench test configuration

  15. Mag. calibration: Chambon

  16. Interface verification at UCB • An interface model has been built and sent to UCB to test I/F to IDPU . • Same Power, Command, analog output interfaces • Power and Cal Mode identification by LED • Cal Signal re-injected to the input • A signal generator can be connected to each input

  17. I&T at UCB • Pre-integrations at UCB • After delivery to UCB (Incoming Inspection, Bench Test) • Sensor in the mu-metal box • Electrical Integration • Power ON and functionnal test • Validation can only be done by analysis of telemetry data

  18. I&T at s/c level • Integration on the spacecraft • Mechanical Integration of the PA, connection to the boom harness • Sensor in the mu-metal box • Electrical Integration (bounding, isolation) • Power ON and functionnal test • Validation can only be done by analysis of telemetry data

  19. SCM tests at s/c level: 1 Initial configuration: The sensor is inside the mu-metal box, connected to the PA via the boom harness Requirement: keep the sensor in the mu-metal box until all experiments are integrated in the spacecraft (mission operation test)

  20. SCM tests at s/c level: 2 • WHAT CAN BE DONE WITH THE SENSOR IN THE MU-METAL BOX? • Verification of the labelling of axis (X,Y, Z) • (Re)-verification of the end-to-end calibration • Phase relation between the 3 components (for the waveforms) • Measure the conducted noise • SCM/EField timing reference [and inter-calibration]

  21. SCM integr. at s/c level: 3 • SENSOR MOUNTED ON THE BOOM • PA saturated by the 50/60 Hz (except in an EMC chamber). • No measurement possible but a major failure would be detectable. • INSTALLATION OF THE MLI: preferably at the last moment, before s/c vibration tests.

  22. EMC tests at s/c level • CETP can help analyse the AC radiated noise around the spacecraft. • A « magnetic sniffer » has been built and delivered to UCB. • In order to avoid the saturation by the 50/60 Hz, the analysis is separated into two bandwidths: below 50 Hz and above 300 Hz (5th harmonic).

  23. SCM integr.; team support • The SCM team will support all critical activities, for the integrations. • However, due to the large number of satellites, a strategy should be implemented to limit the number of travels, cost and time spent • Support EM integrations in any case • The FM will be delivered 3 by 3 and the level of support for each test will be agreed upon with UCB • Capability of remote access/support should be implemented

  24. SCM schedule- Key dates

  25. Status of questions/RFA’s

  26. Status of questions/RFA’s

  27. SCM-6 details • SCM-6 (cnd.) • Summary of THM-SYS-005: • SC(antennas) qualified by CETP (thermal cycling) without vacuum. TV test at s/c level. • PA qualified in temperature (currently done) by CETP, without vac.. TV done at UCB, together with IDPU.

  28. Status of questions/RFA’s

  29. Status of questions/RFA’s

  30. Status of questions/RFA’s

  31. Summary • Ressources (mass & power) are compatible with allocation. • Tight schedule, yet delivery dates for EM and FM are compatible with the schedule of the project. • PA cubes (EM) meet requested performances. PA box passed temp. & vibr.tests ; no problem. • Sensitivity meets specs • Antenna structure (EM) delivered. Meets specs.