Hydrotechnical Design Guidelines for Stream Crossings Alberta Infrastructure and Transportation

Hydrotechnical Design Guidelines for Stream Crossings Alberta Infrastructure and Transportation. Design Parameters. Require Y, V, Q Typical large runoff response Consistent with Physics, History Optimize crossing design. Approach. 1. Channel Capacity 2. Historic Observations

Download Presentation

Hydrotechnical Design Guidelines for Stream Crossings Alberta Infrastructure and Transportation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hydrotechnical Design Guidelines for Stream Crossings Alberta Infrastructure and Transportation

  2. Design Parameters • Require Y, V, Q • Typical large runoff response • Consistent with Physics, History • Optimize crossing design

  3. Approach 1. Channel Capacity 2. Historic Observations 3. Basin Runoff Potential

  4. 1. Channel Capacity • Define typical channel parameters : B, T, h, S • Assign stage : • Calculate V, Q – AT, Manning equation • Governs – most sites with overbank storage

  5. 2. Historic Observations • HW data from bridge files, database • WSC Data – Q, Y for peak events • Storm Database – ID likely response • Governs – large rivers

  6. 3. Basin Runoff Potential • Qp = q x A (upper bound) • q - runoff depth map (cms/km2) • A – contributing • Storage routing • Governs – small basins, steep channels

  7. Compile Hydrotechnical Summary • Concise summary • Summarizes all 3 components • Conclusion : Y, V, Q • Consider u/s and d/s sites (HIS)

  8. Tools • HIS • PeakFlow • Storm On Basin • Global Mapper • Calculation – hydraulics, routing