2006 year. Shipping (#3) of the rest of equipment + materials for 40’s BLM production in April. 22.02 – Shipping Request created in EDH. 23.02 – The documents registered in qualiac. 25.02 - Attachment #3 signed by L.Evans and transferred to IHEP Director N.Tyurin for signature.
E N D
2006 year. • Shipping (#3) of the rest of equipment + materials for 40’s BLM production in April. • 22.02 – Shipping Request created in EDH. • 23.02 – The documents registered in qualiac. • 25.02 - Attachment #3 signed by L.Evans and transferred to IHEP Director N.Tyurin for signature. • 01.03 – 23 packages/10335 kg and CERN documents was ready to go. • 17.03 – Transport by Direct Truck from CERN. • 29.03 – Packages was unloaded in IHEP. • Shipping (#4) of the components for 100’s Head welding. • 1.02.03 – Shipping Request created in EDH. • 03.03 – The documents registered in qualiac. • 04.03 - Attachment #4 signed by L.Evans and transferred to IHEP Director N.Tyurin for signature. • 03.03 – 1 case/50 kg and CERN documents was ready to go. • 17.03 - Transport by Direct Truck from CERN. • 29.03 – Packages was unloaded in IHEP. • Shipping (#5) of the components for 360’s BLM production in May, including the components for 400’s Head welding. • 1. 14.03 – Shipping Request created in EDH. • 2. 15.03 – The documents registered in qualiac. • 3. 16.03 - Attachment #5 was signed by P.Bryant and IHEP Director N.Tyurin. • 4. 15.03 – 3 packages/701 kg was collected by Internal Transport and CERN documents was ready to go. • 23.03 – Transport by Groupage Truck from CERN. • 13.04 – Packages was unload in IHEP
Shipping (#6) of the components for 360’s BLM production in June, including the components for 300’s Head welding. • 1. 4.04 – Shipping Request created in EDH • 5.04. - Attachment #6 signed by L.Evans and transfered to IHEP Director N.Tyurin for signature. • 7.04 - 2 packages/875 kg andCERN documents was ready to go. • 12.04 - Transport by Groupage Truck from CERN. • 06.05 – Packages was unload in IHEP • Shipping (#7) of the components for 360’s BLM production in July, including the components for 1200 Heads welding (July, August, September) and 250 UK Heads. • 18.05 – Shipping Request created in EDH • 18.05. - Attachment #7 signed by P.Bryant and transfered to IHEP Director N.Tyurin for signature. • 23.05 – The documents registered in qualiac. • 24.05 - 6 packages/2305 kg was collected by Internal Transport . • 29.05 - CERN documents was ready • 31.05 Transport by Groupage Truck from CERN. • 27.06 – Packages was unload in IHEP • Shipping (#8) of the components, Detergent and vacuum equipments, including the 50 UK Heads. • 8.06 – Shipping Request created in EDH • 9.06. - Attachment #8 signed by P.Bryant and transfered to IHEP Director N.Tyurin for signature. • 12.06 - 6 packages/965 kg was collected by Internal Transport • 13.06 - CERN documents was ready to go. • 22.06 - Transport by Groupage Truck from CERN • 6. 17.07 – Packages was unload in IHEP
Shipping (#9) of the components for BLM production, including the components for Heads welding. • 1. 18.07 – Shipping was ready. • 2. 18.07 – Shipping Request created in EDH • 3. 19.07. - Attachment #9 signed by P.Bryant and transfered to IHEP Director N.Tyurin for signature. • 4. 21.07 - 7 packages/xxx kg will be collect by Internal Transport .
Shipping #1 of the 40 BLM_IC production (June) • 1. 16.06 – 40 departed from IHEP • 22.06 – 40 arrived at CERN • Shipping #2 of the 360 BLM_IC production (July) • 1. 7.07 – 360 IC are ready to ship. • 2. 19.07- 26.07 – it will expect to depart from IHEP. • 3. 26.07- 4.08 – it will expect to arrive at CERN. • Shipping #3 of the 360 BLM_IC production (August). Transport ordered by CERN. • 1. 7.08 – 11.08 360 IC will be ready to ship. • 2. 14.08 – it will expect to depart from IHEP. • 3. 21.08 – it will expect to arrive at CERN.