410 likes | 620 Views
Elk Run Interchange Design-Build Project S.P. 2505- 48 (TH 52) PROJECT INFORMATIONAL MEETING. September 24, 2009. INTRODUCTION Terry Ward, Mn/DOT District 6 Mn/DOT Project Manager. DISCLAIMER
E N D
Elk Run Interchange Design-Build ProjectS.P. 2505- 48 (TH 52)PROJECT INFORMATIONAL MEETING September 24, 2009
INTRODUCTION Terry Ward, Mn/DOT District 6 Mn/DOT Project Manager
DISCLAIMER What is discussed today is informational only, meant to assist interested teams in the pursuit of this project. The ultimate contract requirements will be included in the Request for Proposals (RFP). There may be changes between now and the time the RFP is issued.
Project Partners • City of Pine Island • Olmsted County • Goodhue County • Federal Highway Administration • Design-Build Proposers • HNTB – Design-Build Contract Development • SRF • Preliminary Geometric Layouts • Environmental Documents • Tower Investments, LLC
Agenda • Project Background • Design-Build Procurement • Design-Build Activity • Questions
Elk Run AUAR • Full Build-Out – 5,157 Acres • Residential – 3,860 acres • Commercial – 680 acres • BioScience – 208 acres • Institutional – 410 • Park and ROW – included in Residential
City of Pine Island • Abraham Algadi, City Administrator • Project Issues • Development Issues
Background http://www.dot.state.mn.us/designbuild/
Background http://www.dot.state.mn.us/designbuild/elkrun/index.html
Background Project Informational Meeting Presentation Preliminary Geometric Layout Utilities Layout Value Engineering Study Tower Right-of-Way Map
Conflict of Interest • Single Point of Contact • terry.ward@state.mn.us
Letters of Interest (LOI) Received Alliant Engineering, Inc. C.S. McCrossan Construction, Inc. Edward Kraemer & Sons, Inc. Hoffman Construction Co. Jacobs Lunda Construction Company Mathiowetz Construction Company Minnowa Construction, Inc. PBS&J Pierce Pini & Associates, Inc.
Letters of Interest (LOI) Received Reilly Construction Co., Inc. SEH Shafer Contracting Co., Inc. TKDA Ulland Bros., inc. URS Valley Paving incorporated Westwood WSN Yaggy Colby Associates
ScheduleTentative – Subject to Change ACTIVITY Due Date Issue RFQ October 2009 SOQ Due Date Oct/Nov Determine Short List Nov/Dec Issue RFP January 2010 Project Letting April 2010
Design-Build Best-Value • Request for Qualifications (RFQ) • Short-listing • Request for Proposals (RFP) • Technical Proposal • POSSIBLE CRITERIA: • Quality • Safety • Innovation • Schedule Integration • Public Relations • Alternate Technical Concepts • Price Proposal
Request for Qualifications • Scheduled to be issued in October • Project Goals: • Design and Construct a Quality product by enhancing Mn/DOT’s Quality Template. • Increase Long Term Performance using Quality Materials and Construction Methods. • Design and Construct a Safe project. • Maximize the design via Innovation for cost effectiveness and efficiency. • Integrate Interchange project schedule with development schedule. • Public Relations
Request for Qualifications • RFP Stipend – 0.2% • Scoring • Responsiveness – 50% • Technical Review of remaining 50% • Mn/DOT Single Point of Contact • terry.ward@state.mn.us
Status • Funding • Right of Way • Tower ROW • Olmsted County Property • Other Parcels • Geotechnical • Utilities • Roadway Geometric Layout • EA Update • Municipal Consent
Design-Build General Discussion Points • Staged Approach to Delivery • All construction completed by 2012. • Co-Housing – probably not. • Teams need to think about communications and issue resolution. • Roadway Design Flexibility • Roundabouts