70 likes | 85 Views
This presentation outlines the progress, challenges, and recommendations in establishing CMAs in Mpumalanga, focusing on the Regional Steering Committee formation, communication and implementation plans, business case development, support requirements, and stakeholder engagement. The update includes details on the establishment of the steering committee, business case development status, support plan needs, and ongoing communication efforts.
E N D
SECOND NATIONAL STEERING COMMITTEE FOR THE ESTABLISHMENT OF CMAs IN SOUTH AFRICA 8 February 2013 CMA Roll-Out Progress Mpumalanga Regional Office (Olifants-Letaba)
PRESENTATION OUTLINE • Progress Report; • Establishment of the Regional Steering Committee including TOR and stakeholder consultation. • Implementation plan and communication plan. • Business case development. • Support plan required for the project. • Challenges and recommendations.
Progress on the implementation plan and Communication plan • Draft communication plan in place • DWA Mpumalanga and Limpopo Regional office are always in touch. • Schedule meetings to engage each to finalised the draft Communication and implementation plan.
Progress of the establishment of the Regional Steering Committee including TOR and stakeholder consultation • Currently in the process of establishing Regional Steering Committee and drafting TOR. • Meetings have been co-ordinated with DWA Mpum to kick start the process • Database in place of stakeholders to be engaged and participate.
Progress on the development of business case. • No draft Business Case for the CMA , meeting is scheduled by Limpopo between the Management Mpumalanga and Limpopo to delegate a person to run the process
Support plan required for the project. • Need financial support from DWA • The CMA will need capacity building from DWA
Challenges and Recommendation • Strengthen communication