Flevoland wide and pure that fits windenergy. Windenergy in Flevoland - te role of the province - the situation in Flevoland - some history in planning - the expectations for the future - how come to resolutions. Windenergy in Flevoland.
E N D
Flevoland wide and pure that fits windenergy
Windenergy in Flevoland - te role of the province - the situation in Flevoland - some history in planning - the expectations for the future - how come to resolutions
Windenergy in Flevoland The role of the province: - Agreement BLOW says 220 MW in 2010 - Facilitating spatial planning process - Consultation in Regional Planning Process
Windenergy in Flevoland the situation in Flevoland - survay windturbines in Flevoland - spatial planning map windenergy
Situation 2003/04 Municipallity Power in MW Number Windturbines Almere 17 10 Dronten 119 92 Lelystad 81 85 Noordoostpolder 32 85 Urk 0 0 Zeewolde 133 165 Flevoland 382 437
Plans for windenergy untill 2005 after 2005 consession planed planed Almere 2535 Dronten 45 Lelystad 45135 Noordoostpolder 45 145 Urk Zeewolde 2090 Flevoland 65205 315
Windenergy in Flevoland • some history in windenergy planning • -1995 / 1996 MER (Environmental Effects) based • on the idee: • a few greater lines and little individual • projects • every municipallity fits its own policy • - 2000 results fixed in Provincial Spatial Plan
Windenergy in Flevoland New / additional elements for Flevoland - Climate policy - Evaluation processing windenergy plan - Information to / discussion with population - New spatial design and plan
Windenergy in Flevoland • some history in windenergy planning • - province facilitate conditions in spatial plan and • management rules • profit: project plans fits due to situation • handicaps: • - diversification and disorderly • - no guaranty for the greater projects
Windenergy in Flevoland some history in windenergy planning The planning process takes still 8 - 10 years smaller projects ( 6 - 10 turbines, < 15 MW) due to quarrel participants greater projects ( > 10 turbines, > 15 MW) different procedures without (fine-) tuning and great amount of participation uncertainly of the policy of the government
Windenergy in Flevoland Expectations for the future - the owners ask for substantial more opportunities - windenergy has grown to an innovative industrial activity - repowering and reconstruction is necessary this gives us a new key for integration interests - due to the measurements we need a new spatial design
Windenergy in Flevoland Expectations for the future - coöperation is necessary - search for new and other locations - request owners: province facilitate repowering and reconstruction Essential for all these actions is communication
Windenergy in Flevoland how to come to resolutions - studyrepowering and reconstruction a model which fit all the individual contributions for all the participants - study new spatial and landscape design an objective model for natural positioning of large windturbines in the landscape
Windenergy in Flevoland how to come to resolutions: WE COMMUNICATE: - forum windenergy: delegate and alderman's - forum public servants - dialog with all the organisations and consultants (due to farmers, habitat, environment, energy, etc.) - wind readings and excursions for the population - windenergy information centre
Windenergy in Flevoland Conclusions: - the province facilitate the planning process - the planning process takes still 8 - 10 years - methods for integrate interest and planning will help / are necessary - communication is essential for the support - the municipalities have the key