1 / 14

presents Project Crimson April 26, 2006

presents Project Crimson April 26, 2006. Sarah Grace Cade Harrelson Cochrane Jamison Libby Probst Justin Williams. Overview. Progress Major Cost Items Grading Erosion Control Storm Sewer System Sanitary Sewer System Water Distribution Paving Railroad Total Cost.

crwys
Download Presentation

presents Project Crimson April 26, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. presentsProject CrimsonApril 26, 2006 Sarah Grace Cade Harrelson Cochrane Jamison Libby Probst Justin Williams

  2. Overview • Progress • Major Cost Items • Grading • Erosion Control • Storm Sewer System • Sanitary Sewer System • Water Distribution • Paving • Railroad • Total Cost

  3. Progress Since Preliminary Report • Water Distribution System Design and Analysis • Sanitary Sewer Systems from Spec Building and Building on Site • Storm Sewer and Detention Pond for 100 Year Flood Event • Added Easier Fire Truck Access to the Building • Erosion Control • Fire Protection • Cost Estimate • Modified Elevations of Proposed Grading in Order to Cut Down on Net Cut and Fill Volumes

  4. MajorCost Items

  5. Grading • REC efficiently raised certain elevations on site in order to cut down on the amount of net cut • Grading Cost Items Include: • Clearing and Grubbing • Top Soil Stripping • Unclassified Excavation • Removing Unsuitable Material • Top Soil Replacement

  6. Clearing and Grubbing: 2 acres Top Soil Stripping: 97,389 c.y.i.p. Unclassified Excavation: 7,008 c.y.i.p. Top Soil Replacement: 2 acres Removal/Stockpile Unsuitable Materials: 15,000 c.y.i.p $ 5,000 $ 438,250.50 $ 70,080 $ 4,040 $ 60,000 Grading Estimates

  7. Silt fences and hay bales Necessary to prevent erosion on site during construction Protects adjacent properties from erosion damage Length of silt fence required: 14,800 l.f. Number of hay bales required: 30 bales Erosion Control

  8. $ 445,770 $ 145,740 $ 211,140 $ 7,200 Pipes Curbs and gutters Drains and Inlets Manholes and Covers Detention Pond * included in excavation costs Storm Sewer System

  9. Sanitary Sewer System

  10. Water Distribution

  11. Paving Costs • Includes all pavement for roads and parking lots Includes preparation of sub-grade Subgrade Preparation Cost: $97,500 Truck Parking and Roadway Employee Parking

  12. Railroad Track Costs

  13. Total Estimated Cost • Total Estimated Cost for Project Crimson: • $4,417,303.55 • Please refer to your handout for the complete cost estimate, unit prices, and amounts of each unit used on site.