1 / 21

Labour Variances - Answers

Labour Variances - Answers. Questions 1 & 2. Question 1. General info 12100 units produced 54900 hours taken Cost £410200 Std time – 4.5 hrs per unit Std Rate - £7.30 per hour. Total labour cost variance. This looks and compares two sets of data:

Download Presentation

Labour Variances - Answers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Labour Variances - Answers Questions 1 & 2

  2. Question 1 • General info • 12100 units produced • 54900 hours taken • Cost £410200 • Std time – 4.5 hrs per unit • Std Rate - £7.30 per hour

  3. Total labour cost variance • This looks and compares two sets of data: • In TOTAL how much should labour have cost us for the production we made (as indicated by the standard)? • In TOTAL how much did labour actually cost us for the production we made? • Adverse = Actual higher than std • Favourable = Actual less than std

  4. Total Labour Cost variance • Std • 12100 x 4.5 x £7.30 = £397485 • Actual = £410200 • Variance = £12715 ADVERSE as our total labour cost was more than std

  5. Labour Total Variance • This can only happen because of one of two reasons (or a combination of both) • Reason 1 – We paid labour at a rate different from standard • Reason 2 – We worked for a longer or shorter period on production (different from standard)

  6. Reason 1 – Labour rate variance • Reason 1 – We paid labour at a rate different from standard • This looks and compares two sets of data: • How much should the labour we used have cost us (as indicated by the standard)? • How much did the labour we used actually cost us? • Adverse = Actual higher than std • Favourable = Actual less than std

  7. Labour Rate Variance • Std • 54900 x £7.30 = £400770 • Actual = £410200 • Variance = £9430 ADVERSE as we paid more per for labour per hr than std • What did we pay per hr? • £410200/54900hr = £7.47

  8. Reason 2 – Labour efficiency variance • Reason 2 – We worked for a longer or shorter period on production (different from standard) • This looks and compares two sets of data: • How long should we have worked for the production we made(as indicated by the standard)? • How long did it actually take for the production we made? • This is a variance worked out in hours as we look at usage and therefore has to be converted to monetary amounts (£)

  9. Labour Efficiency Variance • Std • 12100 x 4.5 hrs = 54450 hrs • Actual = 54900 hrs • Variance = 450 hrs ADVERSE as we used more hrs than std • To complete the variance:- • 450 hrs x £7.30 = £3285 ADVERSE • How many hrs did we take per unit? • 54900hrs/12100units = 4.54hrs

  10. Putting the variances together • Total labour cost variance of £12715 ADVERSE can be subdivided into:- • Labour Rate Variance of £9430 ADVERSE (paid a rate higher than standard) • Labour Efficiency Variance of £3285 ADVERSE (took longer than standard) • (£9430)+(£3285) = ( £12715)

  11. Putting the variances together • Total labour cost variance can be subdivided into:- • Labour Rate Variance • Labour Usage Variance

  12. Give 3 reasons why we may have:- • Paid a price for labour higher than standard • Took longer to produce a unit than set by the standard

  13. Causes of labour cost variances

  14. Question 2 • General info • 11400 units produced • 34700 hours taken • Cost £316400 • Std time – 3 hrs per unit • Std Rate - £9 per hour

  15. Total Labour Cost variance • Std • 11400 x 3 x £9 = £307800 • Actual = £316400 • Variance = £8600 ADVERSE as our total labour cost was more than std

  16. Labour Rate Variance • Std • 34700 x £9 = £312300 • Actual = £316400 • Variance = £4100 ADVERSE as we paid more per for labour per hr than std • What did we pay per hr? • £316400/34700hr = £9.12

  17. Labour Efficiency Variance • Std • 11400 x 3 hrs = 34200 hrs • Actual = 34700 hrs • Variance = 500 hrs ADVERSE as we used more hrs than std • To complete the variance:- • 500 hrs x £9 = £4500 ADVERSE • How many hrs did we take per unit? • 34700hrs/11400units = 3.04hrs

  18. Labour Variances Settings standards and reasons for the variances…

  19. Setting labour variances should include:- • Seasonality • Forseen changes • Efficiency data • Skill of labour force

  20. Adverse or Favourable Labour Variances? • Better quality material • Poorer quality material • Labour rate increase • Labour rate decrease • Unskilled workers • More waste • Improved efficiency • Machine problems • New machines

  21. Better quality material – favourable efficiency Poorer quality material – adverse efficiency Labour rate increase – adverse rate Labour rate decrease – favourable rate Unskilled workers – favourable rate, adverse efficiency More waste – adverse efficiency Improved efficiency – favourable efficiency Machine problems – adverse efficiency New machines – adverse efficiency leading to favourable efficiency

More Related