1 / 13

i2 SCM Factory Planner

助教:鄭歆蓉 ( 分機: 7656) 研究室: MA004 ( 電子化企業實驗室 ) Email : D9701001@mail.ntust.edu.tw. i2 SCM Factory Planner. 電子化企業實習 Week 3 for i2 SCM. 課 程 大 綱. Week 2 複習 訂單生產規劃的安排 替代資源、途程、零件 存貨設定. Week 2 複習. 作業問題說明: 執行後沒有製令單: 原因 規劃內容之英文字母沒有全部大寫! 機台沒有產生負荷: 原因 規劃時間輸入有問題 原因訂單的產品數量太少 沒有機台超出產能:

Download Presentation

i2 SCM Factory Planner

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 助教:鄭歆蓉 (分機:7656) 研究室:MA004 (電子化企業實驗室) Email:D9701001@mail.ntust.edu.tw i2 SCM Factory Planner 電子化企業實習 Week 3 for i2 SCM

  2. 課 程 大 綱 • Week 2 複習 • 訂單生產規劃的安排 • 替代資源、途程、零件 • 存貨設定

  3. Week 2 複習 • 作業問題說明: • 執行後沒有製令單: • 原因規劃內容之英文字母沒有全部大寫! • 機台沒有產生負荷: • 原因規劃時間輸入有問題 • 原因訂單的產品數量太少 • 沒有機台超出產能: • 原因輸入資訊有問題,如製程、BOM表 • 原因訂單不足以讓機台產能超載

  4. 1/5 訂單生產規劃的安排 • 生產開始時間(PST)的計算 • Backward Schedule(由後向前排): • 最遲開始生產時間 Latest Possible Start Time (LPST) • LPST= Due Date – (Setup + Run + Wait)

  5. 2/5 訂單生產規劃的安排

  6. 3/5 LPST • ASSEMBLY_A (由後往前推) • OP1 → M1 —3 (min) • OP2 → M1 —2 (min) 200個 runtime 製造順序: ( ∴由OP2往前推 )

  7. 4/5 LPST ( 又 11/14 (17:20) → 前推 11/14 (7:20) ) ( ∴11/15 (0:00) → 前推 11/14 (≒17:20) ) 200個 × 2 min

  8. 5/5 LPST • ASSEMBLY_C (由後往前推) • OP3 → M2 —8 (min) • OP4 → M3 —4 (min) ( 又 11/12 (15:20) → 前推 11/9 (7:20) ) ( ∴11/14 (7:20) → 前推 11/12 (15:20) ) 600個 × 4 min

  9. 訂單生產規劃的安排 • Forward Schedule(由前向後排): • 最早開始生產時間 Earliest Possible Start Time (EPST) • EPST= max (server start date ,material availability date) • 系統預設PST= later of (EPST,LPST),reduces WIP by not releasing the mfg order too early.

  10. 訂單生產規劃的安排

  11. EPST • 由前往後推 ( ∴由OP3往後推 )

  12. 替代資源、途程、零件 課程內容詳見本週講義

  13. 附 註 • 講義與軟體下載位置: • http://140.118.1.157 • 中文線上學習i2 Factory Planner • 下週請繳交實習課程作業! • Week3作業內容:進行替代作業的設定,再利用Week2提及的CAO,選取一個機台做有限產能規劃,比較說明加入替代作業前後之改善差異,需有規劃前與規劃後的圖片貼上並說明設定哪些參數(要有圖) ! • 作業於下星期上課前mail繳交,作業需標示組別與組員學號及姓名!

More Related