310 likes | 1.02k Views
E N D
1. 1
Hanan El Hadary
Chairman Of Industrial Council For Technology & Innovation Council, Ministry Of Industry
16-18th January 2012, Cairo
2. Contents Why Industrial Parks?
Eco-Industrial Parks Requirements.
Challenges.
Benefits of Eco-Industrial Parks (EIPs).
Example for Case Studies of EIPs attempts in Egypt.
3. Why Eco-Industrial Parks? 3
4. Eco-Industrial Parks Requirements 4
5. 5
6. Benefits of EPIs I 6
7. Benefits EPIs II 7
13. Case Studies of EIPs Attempts in Egypt“Robbiki Industrial Leather and Tanneries City”
14. Vision
Increasing Competitiveness of Egyptian Leather Tanning Products through the relocation of tanneries in Magra El Ouyoun area to a new industrial city under the main objective of developing the Egyptian leather tanning sector and increasing added value for tanned leather products.
Objectives
Creation of 550 new tannery
Investments: 5.5 Milliard EGP
Production: Increasing production of tanned leather products to reach 250 million square feet /year with a percentage increase of 280%
Development: Production of high value added Finished tanned leather products.
Creation of new Job opportunities: 25,000 Worker
Exports: > 300 Million Dollar / year
15. Project Management
Applicant: Ministry of Industry and Foreign Trade (MIFT)
Implementing Agency: General organization for the industrial and mining projects (IMC)
Technological Partners: Technological Cooperation with foreign technological partners for developing production processes, decreasing pollution and increasing value added.
Being a natural continuation of a previous initiative carried out in the framework of the first phase of the Debt for Development Swap Program, the project contributes to the creation of a new industrial specialized in tanning.
17.
Research and Development
Cooperation with foreign technological partners specialized in tanning processes for developing production processes, decreasing pollution and increasing value added.
Liquid Wastewater Treatment Plant: Establishment of WWTP for general effluents (1.2 million m2), Chromium recovery (treating 120 m3/day) and Saline water treatment (treating 600 m3/day)
Solid Waste Treatment: Landfill with a capacity of 33,000 m3/year, duration of 50 years and a solid waste treatment plant with a capacity of 400 tons/day.
Establishment of an Environmental Laboratory.
Training and technical support on Eco-Tanning.
18. Industrial and Technological Services
Establishment of a Leather Tanning Technology Center
Area: 6000 m2
Services:
Training
Consultancies and Technical Assistance.
Quality, environmental, Chemical and Physical testing
Designing production lines and choosing machinery
Leather Tanning Equipment maintenance
Technology Transfer and innovations.
19. 19
20. 20
21. 21
22. Alternative fuel for Cement industry Alternative Fuels in Cement Industry
Tasks
Full assessment for 7 companies for the possibility of project implementation
Feasibility study
Implementation of 2 pilot projects
Outputs
Implementation of the project within 2 pilot activities
Identification of best available technologies
Project dissemination
Beneficiaries:
Technology Transfer and Innovation Council (Associate Partners, GTZ, Fraunhofer Institute)
23. Application of Slag (mixture of elements oxide) in Road Constructions
24. Waste Valorization Projects Project:
Feasibility study for recycling of solid wastes from onion pealing & distillation in El Neanaya Company
Project objective:
Carrying out a feasibility study for recycling of solid waste of onion pealing and distillation by producing compost
Activities of the project:
Installing of compositing system (technical requirements, equipments, area and manpower).
Preparing a pre-feasibility study for installation of composting system.
Identify the available financial packages for financing of the project.
25. Acid Recovery from Wasted Spent Pickling Liquor
27. Installation a Recycling unit for Polyethylene (PE) waste
28. Recycle of Metal Alloys Scrap Company: EIPAL-Egyptian International Company for Aluminium Profiles
This project aims to:
Recycle the scrap metal alloy dies (H 13 Tool Steel) to produce new dies with the same specification of the original.
Solve the national problem of accumulation of steel scrap from all companies of aluminum production companies.
Cost benefit analysis:
Price of H13 Tool Steel Scrap = 2,000 L.E./ ton
Recovery cost = 15,000 L.E./ton
Price of imported H13 Tool Steel = 45,000 L.E/ton
Net Saving = 28,000 L.E./ ton
Annual produced scrap = 24 ton/year
Annual Net Saving = 672,000 L.E.
29.
31. Thank youHanan El-HadaryEgypt National Cleaner Production CentreE-mail: h_elhadary@link.net 31