210 likes | 386 Views
Overview of the AIV test campaign. Willem Luinge Consortium meeting, SVR #2, TRR December 2006, Groningen. Outline. Achievements since SVR Status of integration Pre ILT EGSE/ICC/test infra structure/test scripts Test equipment Miscellaneous Outlook at the near future
E N D
Overview of the AIV test campaign Willem Luinge Consortium meeting, SVR #2, TRR December 2006, Groningen
Outline • Achievements since SVR • Status of integration • Pre ILT • EGSE/ICC/test infra structure/test scripts • Test equipment • Miscellaneous • Outlook at the near future • Full ILT (radiometry, stability, spectral tests) in the last test weeks
Integration activities of HIFI units (1) Mechanical, electrical, command, optical, RF, thermal interfaces to HIFI parts and test equipment; performance check of back ends • WBS, Dec 2005. • Recent IF tuning algorithm works better • HRS integration (10 – 14 April; HRS-H last wk of July) • Performance re-test of back ends hindered by other integrations and Testcontrol problems. Most recent IF stability test are being evaluated.
Integration activities of HIFI units (2) • ICU/OBS integration (ICU: June) • ICU: Boot procedure ok for ILT (OBSM not in place) • Test OBS 4.3 and various units is ongoing; almost all functions for ILT implemented; maintenance still needed • OBS FT: open • FCU FM integration (early July and early November) • Upgrade of power line filtering is implemented (ok with SFT) • Re-qual is open • FPU integration (early Aug) • Was used as detector for LOU (Aug) • Beam measurements complete (Sep) • Open: Chopper scan, fast chop mode, IF feedback, mixer magnet tuning algorithm, generation of diplexer tables, linearity test to be completed/evaluated, chopper response time, thermal settling times • Update and re-run of Integration and FT scripts
Integration activities of HIFI units (3) • LCU FM integration (started 2nd week August) • Integration ICU - LCU FM mechanical, electrical integration and low level command interface tested including electrical interface LCU LSU dummy and LOA dummy • Procedure to upload LCU safety table upload and memory patch operational (various releases tables, MIB and CUS needed) (end of November!) • Passed LO SFT (dummy) • Testmodes for LO ss tested • FM upconverter integration (Oct.), ok. Performance untested. • LSU FM is delivered, TM properties were measured (voltage, IF out put vs. freq and LSU settings) • EIDP’s of FP and LO
Integration activities of HIFI units (4) • LOU FM integration (started 2nd week August) • LOU installed mechanically, checked, cooled, checked again and aligned visually • Check mixer pump level by LOU (controlled by LCU IMD2 and SCOE) for most bands presentation Nick Whyborn • Bands 3a, 7a did not pass integration test (during last cons meeting) • Dismount LO bands & inspection, analysis of failed bands, etc • Nov/Dec: remount other LOA’s and test (IMD2, SCOE), integrate with LCU FM, LSU FM LO presentation • Open: RF integration (pump level, noise temperature) with LSU FM
Pre ILT • Beam measurements of all bands before & after vibration: complete except for analysis and evaluation (dedicated talk) • Linearity tests band 1 are to be evaluated (beam splitter adapted) • Testmode Mixer magnet tuning result differs from the result of a slow scan of magnet current in band 4 (bands 2, 3, 5: open) • IF Stability test: results not fully understood, investigation is not finished • Integration and functional test: are being reviewed taking into account the lessons learned. Then a re-run is needed before delivery • Status gas cell pre ILT tests
EGSE/ICC/test infra structure/test scripts • Testcontrol • Time jitter problems due to undefined time steps in SCOS release and CDMS simulator (1553 bus protocol) • Work around by inserting delays between the commands (flight efficiency cannot be tested) • Bottlenecks from HCSS side seem to have disappeared (TM ingest and other) • New HCSS version makes data almost on line available • A new release has to be made after every change in configuration (MIB, CUS, config file value) • MIB, CUS, config file are in line with current integration phase • New scripts are debugged and tested in parallel set up as far as configuration allows • HK verify scripts ready for test on main line • DB access/IA/know how to use IA is not widespread
Open items Test equipment • Stable operation of FPU cryostat so far, extra safety cycle required? Supply of (liquid) helium? • Programming TEI’s re-imager, PDU // set up and H/C source: to be modified/untested • Matching optics re-imager fit checked (pupil-to-field) alignment to be improved
Miscellaneous issues • Safety issues are in place • No major change in manpower situation, analysis groups installed • Documentation • ILT procedure are split; need editing • Activity sheets added • Modification of the Integration and FT will have an impact on the IST procedures
Outlook • See planning • Integration not completed (set back e.g. LO problems) • Next: complete LO integration • [Pre ILT gas cell measurements] • ILT (=Radiometry) for current bands can start provided • Mixer magnet tuning is in place • Diplexer tables are available • Chopper scan confirms the current assumptions • Other test (settling time etc, chopper response time, fast chopmode) to fill open slots • January: spectral tests and gas cell tests • February: refurbishment etc • March: Band 3, 7 tests • Stability tests and operational procedures mainly overnight
Man power support FM ILT campaign • Mechanical integration: RvdS, ME, LM, WH • Operation, installation of LO sources: NW, WJ, PD, MJ • Alignment issues: BK, MJ, RH, ME • Test equipment handling (vacuum & cryogens): WH, FW • Electrical integration: HS, AN, HG • EGSE, MIB: LD (back up NB, AdJ) • Operators: NB, RH, (MB), back up: AdJ • ICC (software infrastructure, database, IA, etc): AdJ, KE, PZ and others • CUS scripts: DT • Analysis & reporting: Testengineers, system engineer, calibration group, others • General: Contact persons for various subsystems
Documents • Reference documents, VCM • AIV plan • Detailed AIV plan (FM ILT): under configuration control after this review • HIFI ILT Integration and Functional Test Procedure (calls for the scripts): under configuration control after this review • “HIFI ILT Performance Test Procedure” • FM ILT CUS scripts, including documents (e.g. a description: CUS scripts for HIFI FM tests), configuration files • MIB(’s) • IA use cases document and IA tools • Various integration, configuration procedures, manuals • A list of websites was added to the TRR data package • Issue for TRR: content of procedures for ILT and approach