FSU/CI JPII Workgroup Status Report 2 - July 22

FSU/CI JPII Workgroup Status Report 2 - July 22. Current work events. Team work continues in forward, direction over past few weeks. Software Inventory nearly complete. Some documentation efforts currently underway. Report from IT Practicum expected later this week.

danika
Download Presentation

FSU/CI JPII Workgroup Status Report 2 - July 22

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FSU/CI JPII WorkgroupStatus Report 2 - July 22

  2. Current work events • Team work continues in forward, direction over past few weeks. • Software Inventory nearly complete. • Some documentation efforts currently underway. • Report from IT Practicum expected later this week. • Representatives from IT Practicum will be reporting to JPII representatives.

  3. Challenges faced • Little momentum, rate of progress is slowing • Infrequent communications • Collaboration between courses is practically nil • No plan, lack of organized set of clarified goals and objectives

  4. Gantt Chart • Inventory was 50%, now 100% complete • Document was 25%, now 50% complete • No desktop refurbishment • Project closure has begun

  5. Current Project Schedule • Collect and Compile Documentation • Spreadsheets and diagrams • Solicit feedback from team • Begin Project Closure • Create hand-off strategy • Finalize Technology Plan – July 29th • Prepare Presentation – July 31st

  6. Immediate Issues • Continue updates to the Plan including WBS • Prepare for final presentation of plan to various stakeholders