1 / 10

Case Study 6 Streamlining Air Permitting Programs at Hanford

Case Study 6 Streamlining Air Permitting Programs at Hanford. Hanford Background. Established 1943 560 sq miles in Columbia River basin Former weapons production site Now an Environmental Management site. The Challenge.

Download Presentation

Case Study 6 Streamlining Air Permitting Programs at Hanford

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case Study 6Streamlining Air Permitting Programs at Hanford Case S-6

  2. Hanford Background • Established 1943 • 560 sq miles in Columbia River basin • Former weapons production site • Now an Environmental Management site Case S-6

  3. The Challenge • Hanford was preparing 8-10 Notices of Construction (NOCs) each month to comply with CAA requirements • each required 4-6 months to prepare • each required separate regulator review and approval • estimated cost of $1 M/year • significant impact on initiating cleanups Case S-6

  4. The Challenge • Much of the paper work was for standard equipment used in already approved ways • Separate permits were required for standardized, routine activities such as contaminated soils removal and waste transfers Case S-6

  5. Resolving the Challenge • Hanford worked with their regulators to resolve this challenge - save time and reduce funding • Four streamlined processes were negotiated • Categorical Permit • Routine Activities • NOC Short Form • Monthly Meetings Case S-6

  6. Resolving the Challenge • A Categorical Permit: • Standard equipment used in an already approved way does not require a new NOC Case S-6

  7. Resolving the Challenge • A Routine Activities List: • Activities with the potential to emit may proceed with a single regulatory approval • Specifically includes soil removal and waste transfers Case S-6

  8. Resolving the Challenge • An NOC Short Form: • Informally pre-negotiated with regulators • Ensures any potential problems are ironed out before formal submittal • Estimated to save 200 labor hours per NOC over previous practice Case S-6

  9. Resolving the Challenge • Monthly Routine Technical Assistance Meetings: • Creates a positive working environment between DOE and regulators • DOE and regulators discuss projects with very low potential to emit • Regulators have the authority to approve these projects at the monthly meeting Case S-6

  10. Resolving the Challenge • These changes are estimated to save $770,000/year • These changes also reduce schedule risk to Hanford projects Case S-6

More Related