An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. POWERING THE WATER INDUSTRY Issues and Opportunities Dr Jay MillingtonBEng (Hons) PhD E-mail: jay.millington@uwe.ac.uk Phone: 0117 328 6564

  2. Introduction P • Traditional example • Meldon Reservoir • Issues • Banding • ROC vs FIT and energy recovery • Water industry • Regional breakdown • UK wide • Opportunities • Novel approaches • Sutton Poyntz • Esholt • Cotton Valley Photo by: Millington (2011)

  3. UK schemes B Growth? capacity number

  4. Benefits for water industry • Government strategy • Reduce greenhouse gases • Provide energy security • Investment in new technology • Green credentials ↑ Customer bills ↓ • Novel approaches • In addition to ‘win / win’ schemes • Don’t need environmental regulation P P

  5. South West Water – Meldon Reservoir 400kW Francis turbine on scour 30kW KSB centrifugal Pump-as-Turbine Photos by: Millington (2011)

  6. Wessex Water – Sutton Poyntz 15 m , 140 l/s  14 kW Image from: Ecowave 2011, photo by: Millington (2011)

  7. Yorkshire Water – Esholt 9 m , 2700 l/s  180 kW Photo by: Yorkshire Water (2011)

  8. Anglian Water – Cotton Valley 2.6 m , 870 l/s  15 kW Photo by: Millington (2011)

  9. Replace FITs banding? Under FiTs, who’s going to install 100-120kW, 500-599kW and 2-3.6MW schemes? (Not included: on-site electric use, operational costs, interest on loans…)

  10. Downsize for max profit? S 1 more scheme 96kW and £65k more A = 1,826 – (16 x 100) B = (16 x 100 x 19.6p – 1,826 x 15.5p) x 24 x 365 x 35.7% Calcs?

  11. Input electricity • ROCs • Esholt: 10% pre-pumped flow  netted off • FITs • 15kW scheme in Wales: drought pumps 200 hours in last 12 years  ineligible (& can’t opt for ROCs)

  12. Energy recovery ethics G £ £ £ £ £

  13. Other factors • Pump and system efficiency • Operation within OFWAT regulations • Identified opportunities  reality • Other renewable energy sources

  14. Conclusions • If a banding system must be used, FITs should be based on MWh generated to prevent downsizing • FITs should have an allowance for input electricity to ‘net-off’ pre-pumping as with ROCs • Energy recovery systems should be subsidised • Other factors need to be considered

  15. References Arup (2011) Review of the generation costs and deployment potential of renewable electricity technologies in the UK, Study Report – Department of Energy and Climate Change [online, accessed Jun 2012] BHA (2010) England and Wales hydropower resource final report (version 13). DECC and WAG [online, accessed Jun 2012] BHA (2011) List of installations. British Hydropower Association [online, accessed Sep 2011] Burgess, A. (2010) [aburgess@southwestwater.co.uk] Re: Micro hydro in the water industry, 18th August. Email to: Millington, J. [jay.millington@uwe.ac.uk] The UK Renewable Energy Strategy (Command 7686, 2009) [online, accessed Jun 2012] Costyn, J. (2011) Feed-in tariffs: current situation and comprehensive review. BHA Hydropower Conference, Cardiff 29 June 2011: British Hydropower Association [online, accessed Jun 2012] Crompton, C. (2010) The Feed-in Tariff – The consultation story and opportunities for the hydro industry. BHA Annual Conference, Glasgow 13-14 October 2010: British Hydropower Association [online, accessed Jun 2012] DECC (2011) List of generators. Department of Energy and Climate Change [online, accessed Sep 2011] Dent, M. (2010) Stoke Bardolph Energy Crop AD (Anaerobic Digestion) Plant. Severn Trent Water [online, accessed Jun 2012] Elliot, C. (2011) Small Hydro and the FIT. BHA Hydropower Conference, Cardiff 29 June 2011: British Hydropower Association [online, accessed Jun 2012] Entec (2010) Mapping Hydropower Opportunities and Sensitivities in England and Wales – Technical Report, Bristol: Environment Agency. [online, accessed Jun 2012] Great Britain (2009) Electricity, England and Wales. The Renewables Obligation Order. 2009 No.785. London: The Stationery Office [online, accessed Jun 2012] Harrison, G. P. (2004) Developing Renewable Energy within the Water Industry, IDS-Water [online, accessed May 2012] The EU’s target for renewable energy: 20% by 2020 HL Paper 175-I (2007-08) [online, accessed Jun 2012] Howe, A. (2009) Renewable energy potential for the water industry. Bristol: Environment Agency [online, accessed Jun 2012] Hughes, C. (2011) Water resources planning in Wales – potential applications for hydropower. BHA Hydropower Conference, Cardiff 29 June 2011: British Hydropower Association [online, accessed Jun 2012] Hughes, N. (2012) [Noel.Hughes@severntrent.co.uk] Re: Hydro at Elan Valley, 11th June. Email to: Millington, J. [jay.millington@uwe.ac.uk] Kirk, T. (1999) Small scale hydropower in the UK. Water and Environment Journal Volume 13 Issue 3, CIWEM: 207-212 Loening, A. (2010) An early FIT? BHA Annual Conference, Glasgow 13-14 October 2010: British Hydropower Association [online, accessed Jun 2012] Millington, J. D. (2013) Powering the Water Industry. In: Booth, C. and Charlesworth, S., eds. Water Resources in the Built Environment – Management Issues and Solutions. Oxford: Blackwell Publishing Ltd. (forthcoming) Nautiyal. H., Varun, P. R. and Kumar, A. (2010a) CFD analysis on pumps working as turbines. Hydro Nepal, Issue 6, Journal of Water Energy and Environment: 35-37 Nautiyal. H., Varun, P. R. and Kumar, A. (2010b) Reverse running pumps analytical, experimental and computational study: A review. Renewable and Sustainable Energy Reviews Volume 14 Issue 7, Elsevier [online, accessed Jun 2012] REF (2011) List of generators. Renewable Energy Foundation [online, accessed Sep 2011] Singh, P. and Nestmann, F. (2010) An optimization routine on a prediction and selection model for the turbine operation of centrifugal pumps. Journal of Experimental Thermal Fluid Science, Volume 34, Issue 2: 152-164. Singh, P. and Nestmann, F. (2011) A Consolidated Model for the Turbine Operation of Centrifugal Pumps. Journal of engineering for gas turbines and power, Volume 133, Issue 6: Article Number 063002 Water UK (2009) Consultation of REF incentives. Water UK [online, accessed Jun 2012] Williams, A. A., Smith, N. P. A., Bird, C. and Howard, M. (1998) Pumps as turbines and induction motors as generators for energy recovery in water supply systems. Water and Environment Journal Volume 12 Issue 3, CIWEM: 175-178. Williams, A. A., (2010) Centrifugal Pumps as Turbines: a Review of Technology and Applications. In: Hidroenergia 2B.06 [online, accessed Jun 2012] Millington, J. D. (2013) Powering the Water Industry. In: Booth, C. and Charlesworth, S., eds. Water Resources in the Built Environment – Management Issues and Solutions. Oxford: Blackwell Publishing Ltd. (forthcoming)