1 / 11

Powering the Carolinas

Powering the Carolinas. March 19, 2009. Artistic Rendering – Cliffside Modernization. “Sustainable Energy Alternatives and their Impact on Low Income Community”. Overview. Company Information/Diverse Energy Mix Project Overview Construction Status Questions. Duke Energy.

Download Presentation

Powering the Carolinas

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Powering the Carolinas March 19, 2009 Artistic Rendering–Cliffside Modernization “Sustainable Energy Alternatives and their Impact on Low Income Community”

  2. Overview • Company Information/Diverse Energy Mix • Project Overview • Construction Status • Questions

  3. Duke Energy • Fortune 500 Company • Operates in NC, SC, Indiana, Ohio, Kentucky • 4 million customers; 36,000 megawatts • ~18,000 employees • 2.3 million customers in Carolinas; 19,900 megawatts • Diverse energy mix: nuclear, coal, gas/oil fired, hydro

  4. Diverse Energy Mix and Path Forward • Renewable (solar, wind, biomass) to meet NC Renewable Energy Portfolio requirement • Save-A-Watt -- Innovative approach to help meet growing customer demand • New natural gas combined cycle generation at Buck and Dan River Stations - Two 2x1 plants (620MW) • Lee Nuclear Station - Two Westinghouse AP-1000 units (2,234 MW) • Cliffside – Bridge to less carbon intensive future

  5. Existing Cliffside Steam Station • Capacity: 760 megawatts • Location: Cleveland and Rutherford counties, North Carolina • Units 1-4 on line in 1940s (200 MW total) • Electrostatic precipitator (particulate) • Unit 5 on line in early 1970s (560 MW) • Electrostatic precipitator (particulate) • 2002 – Selective Catalytic Reduction (80% removal of nitrogen oxides) • 2010 – Wet flue gas desulfurization (99% removal of sulfur dioxide) and coincident removal of mercury

  6. Cliffside Modernization Project • Retire Units 1-4 (200 MW), add scrubber to Unit 5 • Unit 6 – 800 MW supercritical pulverized coal with innovative arrangement of proven technologies • Unit 6 awarded U.S. Department of Energy advanced clean coal tax credit of $125 million • $1.8 billion estimated cost for Unit 6 • First US coal unit to accept permit condition to be carbon neutral – requires Duke to retire additional 800 MW by 2018 and take other measures as needed

  7. Hitachi “Super-Critical” Boiler Wall-fired, spiral wound boiler w/ 3700 psi steam pressure. Heat rate: 8900 Btu/KWH. Stack Visible emissions: white cloud of water vapor. CEMS for SO2, NOx, Opacity, Hg Selective Catalytic Reduction Reduce NOx by 90% Cooling Towers Reduce withdrawal, eliminates thermal discharge Fabric Filter Baghouse Reduces flyash emissions 99.9% and captures SO3, Hg, HCl, HF Sulfur Dioxide “Scrubber” Removes 99% SO2 & 90% Hg. Gypsum as byproduct. Toshiba Turbine / Generator Most efficient on Duke System Spray Dryer Absorber Ties up SO3, Hg, HCl, HF Unit 6 Design Schematic

  8. Permitting/Environmental • DENR issued water discharge (NPDES) permit 8/13/07 • DENR issued Unit 6 air permit 1/29/08. • Duke submitted landfill construction application 12/18/08 • DENR issued revised air permit 3/13/09 acknowledging Unit 6 will emit less than threshold limits of hazardous air pollutants (1 of 2 utility coal units in US) • Compared with existing Units 1-5 and assuming expected operating conditions, Units 5-6 will emit 80% less SO2, 50% less NOx and Hg while generating over twice the electricity

  9. Cliffside Modernization Project - Construction Status • Cost: $1.8 B ($2,250/kw) • Peak 1,600 construction jobs over 4-year construction period • Construction began 1/30/08; unit expected on line 2012 • 20-30 permanent jobs once the unit comes online • Shaw Group is the engineering, procurement and construction contractor

  10. Questions

More Related