40 likes | 168 Views
SPP EVMS Introduction. Lora Suther 11/15/12. Meeting Agenda. Introduction – Lori Suther ( 10 minutes) EVM process at APL for SPP – Howard Hunter (60 minutes) Discussion/Action Items Adjorn. EVMS Top Level Expectations for Instrument Team Support. Establish strong schedule
E N D
SPP EVMS Introduction Lora Suther 11/15/12
Meeting Agenda Introduction – Lori Suther (10 minutes) EVM process at APL for SPP – Howard Hunter (60 minutes) Discussion/Action Items Adjorn
EVMS Top Level Expectations for Instrument Team Support • Establish strong schedule • Select milestones and set weights • Process is performed for the Phase B pilot program baseline and the Phase C/D baseline • General guidance is the task durations (for the weighting process) should be 2 months or less • Provide monthly schedule updates • Due the 5th calendar day of the month • Submit a monthly estimated actuals report • Due the 10th business day of the month • Work with APL to understand variances