The Director’s Review Results

Review results and upcoming tasks for PD-2/3 preparation, including adjustments to presentations and document preparation. Insights from the Director's Review and L2 Meeting Conclusions discussed. Key dates for project milestones and meeting organization shared.

dcasey
Download Presentation

The Director’s Review Results

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Director’s Review Results Thanks to all who worked so hard. We put on an a very impressive show last week. The PD-2/3 Review is only 5.5 weeks away. We need to make a few adjustments to our presentations and prepare a few additional documents that BNL is asking for. L2 Meeting

  2. Conclusions from the Director’s Review • We obtained our #1 goal which was to proceed to the PD-2/3 review • The talks were very solid. There were some issues associated with how we answered the questions. • Minimal changes to the talks for the PD-2/3 review • We need to describe Scope, Risk, and Contingency early in the talks. It was a point of long discussion in the PM breakout session, and close out report. • In some cases the charge didn’t allow for clean answers to the charge questions, especially as it pertained to 2.X. • We need to scrutinize the charge to the PD-2/3 review closely • We need to tell the committee what satisfies the PD-2/3 requirements at the next review. • It took so much effort to generate the documentation for the Director’s Review, we need to make only incremental changes for the PD-2/3 review. L2 Meeting

  3. sPHENIX Project Calendar • Practice w/ Berndt for Ed, Glenn and Cathy’s talk May 6 • PD-2/3 Review Practice May 15-16 • PD-2/3 Review (MIE only) May 28 (1:00 pm)-May 30 L2 Meeting

  4. Director’s Review Organization • Features of the agenda: • MIE, I&F and silicon upgrades covered by the review • Day-1 is all plenary talks • Day-2, Four breakout sessions • MIE • Infrastructure and Facility • Project Management • Silicon Detectors • One common drill down session in the Project Management breakout sessions. • At the Director’s review we presented 60 talks with, > 60 supporting documents posted. L2 Meeting

  5. Feedback from Director’s Review L2 Meeting

  6. Feedback from Director’s Review -continued L2 Meeting

  7. Director’s Review MIE Breakout L2 Meeting

  8. Director’s Review MIE Breakout L2 Meeting

  9. Director’s Review-continued Timeline for posted talks L2 Meeting

  10. Draft PD-2/3 Agenda L2 Meeting

  11. List of BNL PD-2 Requirements • Project Decision 2 - The Preliminary Design and Project Baseline will be finalized and approved as part of PD-2 (Project Decision 2). A successful PD-2 Review will include the following: • Conduct Preliminary/Technical Design Review • Complete Preliminary/Technical Design Report • Update and approve Project Management Plan (PMP) • Develop a Performance Baseline including Resource loaded schedule • Hazard Analysis Plan • NEPA Determination • Integrated Safety Management Plan • Quality Assurance Program • Propose Funding changes with funding profile • Continue Monthly Reporting include Cost Performance Report • Implement tailored EVMS and change control • Review Project Risk Registry and assess Contingency • Initiate Annual Status Reviews and monthly reporting L2 Meeting

  12. List of BNL PD-3 Requirements • Project Decision 3 (PD-3) includes Approval of the Project Final Design requirements and specifications and Authorization to start Procurement and Construction/Execution/Production. A successful PD-3 Review will include the following: • Conduct Design Review of the final design requirements and specifications • Define and document Design Maturity for each subsystem • Document the Final Design requirements in a TDR or FDR • Update Project Management Plan (PMP) • Preliminary Transition to Operations Plan • Hazard Analysis Report • Quality Assurance Program • Integrated Safety Management Plan • Continue Monthly Reporting include Cost Performance Report • Implement tailored EVMS and change control • Monitor Project Risks and Contingency • Continue Annual Status Reviews L2 Meeting

  13. How Do We Satisfy the PD-3 Requirements to: • Conduct Design Review of the final design requirements and specifications • Define and document Design Maturity for each subsystem “Project Scope:  Do the proposed technical design and associated implementation approach satisfy the performance requirements?  Are the technical designs sound and sufficiently mature to support PD 2/3?”  L2 Meeting

  14. A Final Design Requirements & Specification Review We will hold one for each subsystem (WBS 1.2-1.7) over the next 4 weeks. Each will address the following issues: • Are there any more technical down-selects • Is only Advanced R&D is left. • All safety related issues have been identified and are addressed and resolved. • Are all ICD’s for this subsystem been completed and are they under revision control?  Have they been approved by the Office of System’s Integration? • The 3d Model is finalized and under revision control (detail drawings are in progress) • Have all vendors been identified for major items. • Is this subsystem’s BOE and RLS ready for PD2/3? • Does the electronics have Advanced Schematics & have all major components have been identified. • Can the relevant KPP’s and UPP’s be met by the L2 subsystem as presented? We’ll use these reviews to write a engineering review report and create a design maturity score. Internal reviews 2-3 hours each. L2 Meeting

  15. Required for PD-2/3 Review • Completed TDR, PMP, RR and RMP • PDRs done • A Final Design Requirements and Specifications review • A Preliminary Transition to Operations Plan • Short QA Plan for a WBS L2’s (each signed by C. Gortakowski) • BNL has also asked for a document that flows down the sPHENIX physics requirements to the detector performance and specs. We need to provide the PD-2/3 committee with these documents. L2 Meeting