An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. T-76.115 Project Review X-tremeIT I2 Iteration12.02.2004

  2. Project status (7 min) achieving the goals of the iteration project metrics Used work practices (5 min) Completed work (30 min) presenting the iteration’s results demo Plans for the next iteration (3 min) Agenda X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  3. Status of planned goals of the iteration • Goals: • Test cases and testing of GUI +- • Integrate system modules ++ • Implement more use cases ++ • UC-01/1.1 Creating objects – to be updated with more object types • Add text box to objects • UC-01/1.2 Removing objects • UC-01/1.4 Removing dependencies • UC-02/1 Saving process diagram to XML file • UC-03 Removing process diagram • UC-04 Viewing process diagram • UC-09 Printing process diagram • Testing +- X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  4. Status of planned deliverables of the iteration Deliveries: • Implemented software • Updated: • project plan • requirements document • technical specification • Test cases • Test report • User’s manual (Seppo) • Progress report X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  5. Realization of the tasks • Deviations • Architectural design • Unplanned (LOC Calculation) • Not started I2 tasks (was not reported) X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  6. Working hours by person X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  7. Project progress tracking and control X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  8. Quality metrics Bug metrics • Small bugs were found while compiling the code • Insignificant logical bugs eliminated right on the programming sessions • 3 bugs reported to Bugzilla, 2 corrected X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  9. Configuration management • JUnit tests for every class will be written in the next phase. • We did not need Ant. • Small problems with Eclipse and CVS, but everything has been solved. X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  10. Software metrics NCSS = Non Commenting Source Statements X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  11. Risks • Risk management • risks evaluation forms • Risks analysis (Red , Yellow, Green) • No New risks reported X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  12. Work practices • Requirements elicitation and analysis (Konstantin) • Usability tests (Roman) • Architecture design (Vlad) • Pair programming (Aleksandr) X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  13. Pair Programming After Iteration 1 After Iteration 2 X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  14. Software demo • GUI • Controller • XML parser • Engine X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  15. Plan for the next iteration • Goals: • Implement more use cases • UC-02/1 Saving process diagram locally • ? -> to be agreed with customer after project review meeting • Careful system testing • Bug fixing • Peer testing • System is ready to deliver to the customer • Deliveries: • Implemented software • Updated: • project plan • requirements document • technical specification • test cases • user’s manual • Test report • Peer test plans • Peer test reports • Progress report X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  16. Plan for the next iteration X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

  17. Thank you! Questions, comments? X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr