T-76.115 Project Review. Sotanorsu PP Iteration 30.10.2003. Project status (15 min) - achieving the goals of the iteration - project metrics Used work practices (10 min) Completed work (5 min) - presenting the iteration’s results Plans for the next iteration (5 min)
E N D
T-76.115 Project Review Sotanorsu PP Iteration30.10.2003
Project status (15 min) - achieving the goals of the iteration - project metrics Used work practices (10 min) Completed work (5 min) - presenting the iteration’s results Plans for the next iteration (5 min) Comments and questions (5 min) Agenda
Status of planned goals of the iteration Specified in the project plan: making the first version of project plan - OK define project practices - OK build up infrastructure for forthcoming phases - OK now - problems with CVS and TWiki familiarizing oneself with the project problem domain - OK making requirements specification on general level - OK Other goals stay in schedule - the project was about one week late start personal SE assignment work - three already presented make a hardware list - OK - need to know compatible products
Status of planned deliverables of the iteration Project Plan OK - the rest of the personal SE assignments missing - hardware list is incomplete: Requirements specification OK Other documents (Twiki) - Meeting minutes OK - Personal assignments OK
- lectures were quite unpopular requirements took more time than expected travelling took time from other activities workload of ”writing project plan” was underestimated Realization of the tasks
Working hours by person Realized hours in this iteration Plan in the beginning of this iteration Simo’s role as a project manager took more time - also built infrastructure no dramatic differencies Latest plan (inc. realized hours and other updates)
Changes to the project Original idea was to use WLAN for PDA connection This was changed to bluetooth
Risks Eiri Valanto is responsible for risk management Main risks in the project plan All risks are in control ”Internal deadlines are not met” is actually realised New risks? Architecture design starting Requirements Specification
Work practices mandatory practices: time reporting switched from Trapoli to plain text files personal SE assignments team organization communication practices architectural design Bug reportation will be started in phase I1.
Results of the iteration Project plan Requirements specification
Project plan • Background of the project • Project organization • Project goals • Project resources • Project practices and tools • Iterations
Plan for the next iteration Goals design architecture of both subsystems implement core architecture implement basic functionality in both subsystems plan and start testing have the rest of personal SE assignments ready