CF Organization & Schedule. Status Scope CF Organization FY 05 CF Organization FY 06 Construction Schedule. Status. Sector 20 – Title III to commence June 1, 2005 MMF – Title III to commence June 15, 2005 Title II – (RSY-CLOC) is underway Geotechnical Baseline Report award is imminent
E N D
CF Organization & Schedule Status Scope CF Organization FY 05 CF Organization FY 06 Construction Schedule
Status • Sector 20 – Title III to commence June 1, 2005 • MMF – Title III to commence June 15, 2005 • Title II – (RSY-CLOC) is underway • Geotechnical Baseline Report award is imminent • Environmental analysis of site characterization • CMGC to award June 2005
SLAC Site Plan SLAC Main Gate Pep Ring Road Bldg #081 - MMF Sector 25 Sector 20 Upstream LCLS General Work Boundary Research Yard
Below Grade Plan Beam Transport Hall Near Hall Undulator Hall XRTDT Far Hall
LCLS Site Plan Spear Future Office Space Pep Ring Road SLC Office Complex Undulator Hall Research Yard Survey Tower NEH Beam Transport Hall SLC Tunnel Beam Dump Front End Enclosure Future Beam Lines X-Ray Transport Pep Tunnel
CLOC Floor Plans CLOC Exterior Elevations • Headcount of CLOC Personnel = 284 • Capacity of Conf Center = 150 • Gross square footage of CLOC (offices and labs) = 68,800sf
LCLS CF Construction Schedule • Added additional time for CM/GC procurement phase • DOE approval for CM/GC SOW – (in progress – request return date April 20, 2005) • Major construction phase FY 06 at 30 months duration • Beneficial Occupancy dates are key to technical system interfaces • Site-work at NEH is key!