1 / 15

Managing a Successful Mechanical System project

Managing a Successful Mechanical System project. Following design – what next?. Construction Procurement . Deciding which procurement strategy is best Lowest price or greatest value? Reviewing the bids/proposals Selecting the best contractor for the project.

deliz
Download Presentation

Managing a Successful Mechanical System project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing a Successful Mechanical System project Following design – what next?

  2. Construction Procurement • Deciding which procurement strategy is best • Lowest price or greatest value? • Reviewing the bids/proposals • Selecting the best contractor for the project

  3. Other decisions early in the project • How much inspection is required and who is the best qualified to perform the inspections • Who should review the material/shop drawing submittals • Is commissioning required and who should do the commissioning?

  4. How much inspection is required and who is the best qualified to perform the inspections • Can this be done in-house? • Should the design engineer be involved in the construction inspections • Should this work be done by an independent construction management firm

  5. Who should review the material/shop drawing submittals • Should the design engineer review the submittals? • Should the construction manager review the submittals?

  6. Is commissioning required and who should do the commissioning? • Based on the complexity of the mechanical system, a decision needs to be made as to how much commissioning is required and who should do commissioning • A/E commissioning • Construction manager commissioning • Construction contractor commissioning

  7. A/E commissioning • Advantage of having someone familiar with the design doing the commissioning • Advantage of having someone that can make adjustments to the design if corrections are necessary • One party to depend on for system operation

  8. Construction manager commissioning • Independent review of the system • Can determine if operational problems are related to design or construction • Needs to be able to work with the design engineer if problems are found

  9. Construction contractor commissioning • Small project • Projects that are not too complex

  10. Progress of work • Submittal and shop drawing reviews are early in the project • Responding to Requests For Information (RFIs) is ongoing throughout the entire project • Construction inspection throughout the project • Commissioning – also throughout the project

  11. Pre-close in inspection • Anything that will be concealed by finished construction needs to be inspected prior to installation of the finishes • Pressure testing of ductwork • Pressure testing of mechanical piping systems • Inspection of insulation

  12. Final inspection • Final inspection by someone other than the person charged with the day to day administration/inspection of the construction work • Correction of final inspection defects and omissions

  13. Final Commissioning • Verification of all operational features of equipment • Verification that everything is installed in accordance with the contract • Verification that everything is operating as per the design • Verification that all conditions in the original scope are met with the construction

  14. Closeout documentation Operation and Maintenance manuals Training on the equipment Warranty information As-built drawings Testing records and commissioning results

  15. SE Regional Archives

More Related