Whitetail Gas Storage Project. December, 2007. Tarpon Gas Storage, LP. Tennessee Gas Pipeline . Texas Eastern Pipeline. Target Area for Tarpon Whitetail Gas Storage. Tarpon Whitetail Gas Storage. WGS. Mississippi. Jackson. Depleted Gas Reservoir Opportunity
E N D
Whitetail Gas Storage Project December, 2007
Tennessee Gas Pipeline Texas Eastern Pipeline Target Area for Tarpon Whitetail Gas Storage Tarpon Whitetail Gas Storage WGS Mississippi Jackson • Depleted Gas Reservoir Opportunity • Strong water drive reservoir located in the Black Warrior Basin • Reservoir Depth: ~ 3,400 - 3,600 feet • Approximate Working Gas Capacity: ~9.0 BCF Texas Eastern Sonat Tennessee
Whitetail Gas Storage Overview • Depleted Gas Storage Reservoir near the City of Aberdeen in Monroe County (NE Mississippi) • Gas Storage Services on Texas Eastern Transmission, LP (TETCO) • Highest Standards of Safety and Environmental Impact Mitigation • Working Gas Capacity: ~9 BCF (depending on approved Pressure Gradient)
Storage Services Contemplated • Firm Leasing • Interruptible Park & Loan • Firm Park & Loan • Service Open Season in December
Whitetail Reservoir and Facilities • Fourteen Injection/Withdrawal Wells on 2 Well Pads • Construction of ~1 Mile of 16” Diameter Intra-Site Pipeline • Installation of Compression and Related Surface Facilities • Construction of ~5 Miles of 24” diameter West Header Pipeline • Interconnection with TETCO South of Egypt Compressor Station
Whitetail Development Timeline File FERC 7 (c) Certificate Target Date: 12/17/07 Begin Construction Jul 2008 Gas Storage Field viability April 2007 Fully Operational April 2009
Whitetail Attributes • Depleted Reservoir with Good Deliverability Characteristics (Multiple Cycles per Year) • Geographical Location Reduces Delivery Disruptions from Hurricanes • Safety Advantages associated with Depleted Reservoir • Rural Site (Mostly Cultivated Fields) • Economic Benefits to Monroe County
Whitetail Project Status • Tarpon Whitetail Licensed to Operate in MS • Reservoir Optimization Analysis Underway • Pressure Gradient Will Impact Outcome • Civil Engineering Work On-going • Surface Equipment Specified/Bid • Developing Sub-Surface Program • On-site Well Analysis Complete • Discussing Transfer of Inactive Wells • Existing Well Re-entry • New Injection/Withdrawal Wells