RAJASTHAN STATE ROAD DEVELOPMENT AND CONSTRUCTIONS CORPORATION LTD. JAIPUR. HANUMANGARH SURATGARH ROAD, MDR-103 (KM 0/0 TO 50/0 & SURATGARH BYPASS 4KM). DEVELOPMENT ON PPP (BOT) MODEL. Hanumangarh Suratgarh Road, MDR-103. PROJECT LOCATION.
E N D
RAJASTHAN STATE ROAD DEVELOPMENT AND CONSTRUCTIONS CORPORATION LTD. JAIPUR HANUMANGARH SURATGARH ROAD, MDR-103 (KM 0/0 TO 50/0 & SURATGARH BYPASS 4KM) DEVELOPMENT ON PPP (BOT) MODEL
Hanumangarh Suratgarh Road, MDR-103 PROJECT LOCATION The project corridor Hunumangarh-Suratgarh, MDR, starts at Hanumangarh in Hanumangarh district, traverses through Pilibanga taluka of Hanumangarh which further runs across Suratgarh ,Sri Ganganagar district through, Rang Mahal and Ratanpur Rataan and connects the historical fort city of both historical places. Starting point of the corridor is from junction of 0 km in the heart of Hunumangarh and ends at 50 km at Suratgarh. At the beginning the road passes through commercial and residential zone of the urban area of Hunumangarh on the both the sides of the road. End point of the corridor is well maintained rotary on the three legged junction where right approach connects to the bypass to NH-15 (one side Bikaner (175Km) and other side Sriganganagar) LOCATION Page 2
Hanumangarh Suratgarh Road, MDR-103 LOCATION Page 3
Hanumangarh Suratgarh Road, MDR-103 NECESSITY • Improved connectivity • Development of the surroundings • Reduce the present Traffic Load • Sustain the future growth Page 4
Hanumangarh Suratgarh Road, MDR-103 LENGTH (Km) • Total Length of main Link is 48.5 Km • Suratgarh Bypass started at Ch 49+675 of Total Length 4 Km upto Manaksar Chouraha. • Total Length of Hanumangarh Bypass is 10.5 Km, however, it has been included up to 2.4 km i.e. Maharaja Agrasen Chouk. • - Page 5
Hanumangarh Suratgarh Road, MDR-103 SCOPE • Preparation of Detailed Project Report • Site reconnaissance • Road Inventory • Pavement Condition • Soil Investigation • Topographical Survey • Improvement Proposal • Finalization of Bypass Alignment • Detailed Design of Geometrics, Pavement & Structures • Detailed design of Road Appurtenances • Preparation of BOQ • Calculation of BOT/Annuity. Page 6
Hanumangarh Suratgarh Road, MDR-103 EXISTING WIDTH PRESENT STATUS Page 7
Hanumangarh Suratgarh Road, MDR-103 Overlay thicknesses PRESENT STATUS Page 8
Hanumangarh Suratgarh Road, MDR-103 VILLAGES ENROUTE PRESENT STATUS Page 9
Hanumangarh Suratgarh Road, MDR-103 EXISTING STRUCTURE Culverts (Including both Bypasses) PRESENT STATUS Page 10
Hanumangarh Suratgarh Road, MDR-103 Minor Bridges PRESENT STATUS Page 11
Hanumangarh Suratgarh Road, MDR-103 Major Bridges PRESENT STATUS Page 12
Hanumangarh Suratgarh Road, MDR-103 EXISTING LEVEL XINGS PRESENT STATUS Page 13
Hanumangarh Suratgarh Road, MDR-103 EXISTING LEVEL XINGS AMARPURA RATHAN RANGMAHAL Page 14
Hanumangarh Suratgarh Road, MDR-103 Thickness of new pavement PROPOSED DEVELOPEMENT Page 15
Hanumangarh Suratgarh Road, MDR-103 PROPOSED BYPASS PROPOSED DEVELOPEMENT Page 16
Hanumangarh Suratgarh Road, MDR-103 PROPOSED BRIDGES PROPOSED DEVELOPEMENT Page 17
Hanumangarh Suratgarh Road, MDR-103 PROPOSED ROB PROPOSED DEVELOPEMENT Page 18
Hanumangarh Suratgarh Road, MDR-103 Project Cost – 225cr. (Road 171 + Structure 54) Construction Period – 2 yearsConcession Period – 26 YearsAnnuity - NA Page 19
Hanumangarh Suratgarh Road, MDR-103 TRAFFIC Page 20
Hanumangarh Suratgarh Road, MDR-103 TRAFFIC Page 21
Hanumangarh Suratgarh Road, MDR-103 PROPOSED CROSS SECTION (RURAL) Page 22
Hanumangarh Suratgarh Road, MDR-103 PROPOSED CROSS SECTION (URBAM) Page 23
Hanumangarh Suratgarh Road, MDR-103 ABSTRACT OF COST OF DEVELOPMENT Page 24
Hanumangarh Suratgarh Road, MDR-103 ABSTRACT OF COST OF DEVELOPMENT (2-LANE) Page 25
Hanumangarh Suratgarh Road, MDR-103 ABSTRACT OF COST OF DEVELOPMENT (4-LANE) Page 26
Hanumangarh Suratgarh Road, MDR-103 Presumed tollable traffic Assumed traffic growth per year 5% Page 27
Hanumangarh Suratgarh Road, MDR-103 Toll palza locationS Page 28
Hanumangarh Suratgarh Road, MDR-103 Possible mode of development Amounts are in lac Page 29
Hanumangarh Suratgarh Road, MDR-103 DATE OF SUBMISSION OF DPR Second week of July. Page 30
Hanumangarh Suratgarh Road, MDR-103 LIKELY DATE OF START OF WORK September 2010. Page 31