Results from the 'S1-Global' cryomodule tests at KEK (8-cav. and DRFS operation)

Results from the 'S1-Global' cryomodule tests at KEK (8-cav. and DRFS operation). Shin MICHIZONO (KEK). Outline I. 8-cavity installation (S1 global) Total eight cavities are installed. Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) No beam operation

devona
Download Presentation

Results from the 'S1-Global' cryomodule tests at KEK (8-cav. and DRFS operation)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  2. LOLB-2 (June, 2011)

  3. LOLB-2 (June, 2011)

  4. LOLB-2 (June, 2011)

  5. S1 Global LLRF for 8 cav. operation • All the cavities are driven by 5 MW klystron. • Digital LLRF system using an FPGA board on cPCI. • 10 16bit-ADCs are installed. LOLB-2 (June, 2011)

  6. loaded-Q interlock • Calculate the loaded Q from the decay of the rf signal • The interlock works well and contributes to the lower heat load to the cryogenics. RF off Done RF off LOLB-2 (June, 2011)

  7. Real time detuning monitor • The real time detuning monitor is quite helpful to adjust the Piezo tuners. detuned LOLB-2 (June, 2011)

  8. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  9. Stabilities at 26 MV/m operation By T. Matsumoto • 0.0067%rms(in amplitude),16.5mdeg.rms(in phase) @690~1590us LOLB-2 (June, 2011)

  10. RF stabilities during 2H operation • Vector sum amplitude and phase are kept constant during 2H operation. Gradient Amplitude stability Phase stability LOLB-2 (June, 2011)

  11. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  12. LOLB-2 (June, 2011)

  13. Dynamic detuning compensation with piezo • Piezo works well to compensate the dynamic detuning LOLB-2 (June, 2011)

  14. Detuning change during 2H operation • DESY: 33Hz, FNAL:12~38Hz, KEK: 5~10Hz FNAL quench DESY KEK KEK KEK KEK • Rather stiff at A-1~4. (~1/4 compared with C-1~4) LOLB-2 (June, 2011)

  15. Ql change during operation • Ql changes are also observed at KEK. • This is still open question. (difficult to explain by only coupler lod) FNAL DESY KEK KEK KEK KEK LOLB-2 (June, 2011)

  16. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  17. Cavity equation • The cavity should satisfy the differential equation. • In addition directivity (~20dB) of rf monitor-coupler should be concerned. • -> The directivity can be corrected using this formula. LOLB-2 (June, 2011)

  18. Quench phenomena • Loaded Qs are calculated from cavity differential equation. • Only the end of rf pulse shows the quench. • Rather stiff at A-1~4. (~1/4 compared with C-1~4) LOLB-2 (June, 2011)

  19. Quench phenomena (2) • Detuning change at C-4 affects the VS leading to C-1 Quench LOLB-2 (June, 2011)

  20. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  21. LOLB-2 (June, 2011)

  22. LOLB-2 (June, 2011)

  23. LOLB-2 (June, 2011)

  24. Schematic of the DRFS at S1-global DRFS #1 DRFS #2 MA modulator LOLB-2 (June, 2011)

  25. DRFS klystron and WG system with module • Feb.8 : LOLB-2 (June, 2011)

  26. DRFS klystron and WG system • Feb.8 : Phase shifter Phase shifter LOLB-2 (June, 2011)

  27. Some photos Modulator on the ground DRFS #2 DRFS #1 LOLB-2 (June, 2011)

  28. Some photos (2) MA modulator DRFS #1 Phase shifter LOLB-2 (June, 2011)

  29. HLRF and LLRF LLRF rack is located just downstream of cryomodule -> radiation dose will be measured. Magic-T and WG system LOLB-2 (June, 2011)

  30. S1 Global 3rd stage (DRFS)(1) • Digital system is located in the tunnel • Fast interlock (and Arc detectors, VSWR meter) are located on the ground. • cPCIs are used for the monitor and also they are the backup digital system. LOLB-2 (June, 2011)

  31. Field regulation with uTCA • cERL like uTCA FPGA system was installed. • An FPGA board have 4 16-bit ADCs and 4 16-bit DACs. • Two cavity-pickups, klystron output, reflection are observed. • The system was located in the tunnel. LOLB-2 (June, 2011)

  32. RF distribution at DRFS • One klystron drives two cavities. • Circulator-less system. • Same (amplitude and phase) reflection signals go to the dummy load.(blue line) • Un-balanced reflection signals move to the klystron. (red line) • -> careful operation is required to protect the klystron. • Phase-shifters are introduced to evaluate the system. (not to be used at ilc-DRFS) LOLB-2 (June, 2011)

  33. Circulator-less system • Elimination of circulators are proposed at DRFS. • The study to eliminate the circulators were partly carried out at STF-1. However, there was a big circulator between cavities and a klystron. • This is the first time to eliminate all the circulators. With circulators Without circulators Cavity input | Vf | | Vf | Cavity input exists even after RF off Results at STF-1 Normalized by klystron output Vf amplitude ratio (%) Vf amplitude ratio (%) LOLB-2 (June, 2011)

  34. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  35. Cavity equation • The cavity should satisfy the differential equation. • In addition directivity (~20dB) of rf monitor-coupler should be concerned. • -> The directivity can be corrected using this formula. LOLB-2 (June, 2011)

  36. Diagnostics (Ql evaluation) • The simple Ql estimation from decay curve does not work when the rf input exist after rf switched off. • The calculated Ql values agree well between filling and decay. • Although simple Ql calculation is useful for interlock, this is not sufficient for diagnostics. Ql from decay Cav1 Ql at filling Ql at decay Cav2 LOLB-2 (June, 2011)

  37. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  38. Typical operation of VS control Pf Pb to kly. • Under the low reflection condition, VSWR is ~1.1. LOLB-2 (June, 2011)

  39. Detuning and Ql under typical operation Red:Ql by decay Cav. C-1 Blue: Ql by cavity eq. Cav. C-2 • Loaded Qs calculated simple time decay are not correct. LOLB-2 (June, 2011)

  40. Un-matched operation with VS control(different detuning) Pf Df1>Df2 Pb to kly. • Reflection to the klystron is ~25kW (max VSWR=3) • Vector sum is still regulated. (0.04%rms, 0.06deg.rms) LOLB-2 (June, 2011)

  41. Un-matched operation (detuning and Ql) Blue: Ql by cavity eq. Cav. C-1 Red:Ql by decay Cav. C-2 • Although Qls by decay show low-value, Qls based on cavity equation show reasonable values. LOLB-2 (June, 2011)

  42. Un-matched operation with VS control(different waveguide-length) Pf Df1~Df2 Pb to kly. • Reflection to the klystron is ~20kW (max VSWR=2.8) • Vector sum is still regulated. (0.015%rms,0.07deg.rms) LOLB-2 (June, 2011)

  43. Un-matched operation (detuning and Ql) Cav. C-1 Cav. C-2 • Ql by decay: ~4e6 • Ql by cavity equation: ~2.5e6 LOLB-2 (June, 2011)

  44. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  45. Adaptive detuning correction via EPICS • DC piezo bias is controlled every ~2 min. for detuning correction. • The detuning after filling were kept constant Detuning correction • Even these simple (and slow) detuning correction looks promising to compensate the long-time detuning fluctuation (microphonics). Piezo output to change from 0Hz to -50Hz LOLB-2 (June, 2011)

  46. RF waveform and detuning LOLB-2 (June, 2011)

  47. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)

  48. RF overhead @flat-top 10% overhead necessary. Average power 11% If we allow 50Hz detuning, 7% overhead is required . 4% Variation inside pulse Minimum 3% rf overhead is necessary. LOLB-2 (June, 2011)

  49. Long term stability (microphonics) A-2 No piezo control Adaptive control No piezo control A-3 • Microphonics are about 3~5Hz rms. • Since KEK cavities are stiff enough, the effect of adaptive piezo control is not clear. LOLB-2 (June, 2011)

  50. Results from the 'S1-Global' cryomodule tests at KEK(8-cav. and DRFS operation) Shin MICHIZONO (KEK) • Outline • I. 8-cavity installation (S1 global) • Total eight cavities are installed. • Rather short time operation (for total 3 months, Mon. to Fri. from 1PM to 7PM.) • No beam operation • With circulators at individual input coupler • Dynamic detuning control with piezo • Vector sum operation • Quench analysis • II. DRFS operation (aiming for ilc) • One klystron drives two cavities. • Total 2 klystrons are used. • No beam operation • Without circulators • Dynamic detuning control with piezo • Slow detuning control with piezo • III. Future plan • Related topics • Performance • Diagnostics • Piezo control(8cav. &DRFS) • Quench phenomena (8cav. &DRFS) • Rf overhead (8 cav. &DRFS) • Circulator-less (DRFS) LOLB-2 (June, 2011)