Power Curtailment Plan. ComEd CLR7 5/11/2011. One Time, One Hour Test. Between June 1 st and September 30 th Usually in August Normal Work Days 2 Hour Warning By Contract (2 days?) Invoke Bob’s Plan “A” & drop >15MW
E N D
Power Curtailment Plan ComEd CLR7 5/11/2011
One Time, One Hour Test • Between June 1st and September 30th • Usually in August • Normal Work Days • 2 Hour Warning By Contract (2 days?) • Invoke Bob’s Plan “A” & drop >15MW • New criteria is to get lab to 43.5 MW to break even. (46.5 MW we owe $120k, $40k/MW) • Labs Running at ~61MW (Drop 17.5MW)
Plan “A” • Turn off Main Injector and Booster as if they were going into access. • Turn off (stop ramping) Switchyard, NuMI, MiniBooNE, PBar, and any other power supplies since beam will be unavailable. • The Tevatron Store will remain circulating, if we have one. • The Stack (PBar) and Stash (RR) will also remain circulating.
Plan “A” Continued • No New Bakes or large power loads added at IB-1, IB-4, NML, MP9, or other areas. • Call Division/Section Contacts (Update Contact List)
Events - Fine Print • Maximum of 15 actual curtailments Events • We have never had one • We don’t have to participate • Weekdays between 1100 and 1900 • Each Event limited to 8 hours • If we participate in Event, no test required • No predetermined level, we do our best