Jeremy West Sr. Operations Engineer. Enhanced Curtailment Calculator (ECC). Learning Objectives. History behind need for ECC Review ECC proposed functionality ECC interactions with scheduling. The Evolution of SOLs/IROLs in the West. Prior to 2011: No IROLs identified in the West
E N D
Jeremy WestSr. Operations Engineer Enhanced Curtailment Calculator (ECC)
Learning Objectives • History behind need for ECC • Review ECC proposed functionality • ECC interactions with scheduling
The Evolution of SOLs/IROLs in the West • Prior to 2011: • No IROLs identified in the West • RC and TOPs primarily focused on Major WECC Transfer Paths • Equipment/Facility ratings not considered SOLs • April 2012 – RC SOL Methodology revised • SOLs – facility ratings, bus voltage and stability limits • IROLs – process for identification • August 2013 – RC SOL Methodology second revision • Improve processes for determining IROLs • Greater emphasis on determining acceptable pre- and post- Contingency operating conditions
Enhanced Curtailment Calculator (ECC) • What issues does ECC address? • webSAS Limitations • UFMP restricted to 6 Qualified Paths • TDFs based on seasonal models • Increased system awareness • Visibility of untagged flows • Incorporation of outage info (gen and trans) • Compliance • Address IRO and TOP standards • Address September 8 event recommendations
ECC Phase I • Provides situational awareness to RC • Current hour – uses SE for topology • Look ahead hours – starts with SE topology but adds generator and transmission outage data • Visualizes “layers” of impacts • e-Tags • Dynamic Transfers • Network & Native Load • Market Flows • ACE / RBC Flows • RSG Flows
ECC Phase II • Implementation of FERC-approved curtailment methodology • Transition from webSAS to ECC for support of UFMP on 6 Qualified Paths • Redispatch and curtailment to manage congestion on defined elements as needed to support reliability • Collaborative effort with entities when implemented
ECC Interactions with Scheduling • e-Tagging • Source/Sink Granularity BA A BA A BA B BA B = Contract (On) Path = Off Path
ECC Interactions with Scheduling • Dynamic Transfers • Catalog Effort for Peak • Telemetry • Forecast Data • Dynamic Schedules – energy profile accuracy? • Pseudo-Ties – options e-Tag Build in ECC EIR Registration
ECCTF • Task Force advising Peak on ECC • Reorganized under Peak MAC • Chair → Raj Hundal • Meetings open to public
ECC Information https://www.peakrc.com/whatwedo/ECC/Pages/default.aspx