Cascade diagrams – Example 1

Cascade diagrams – Example 1. The table below shows the tasks involved in a project, with their durations and immediate predecessors. Cascade diagrams - Example 1. Initially, put all tasks at their earliest possible time. A. B. A, B and C can all start at time zero. C. D. E. F. G.

dian
Download Presentation

Cascade diagrams – Example 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cascade diagrams – Example 1 The table below shows the tasks involved in a project, with their durations and immediate predecessors.

  2. Cascade diagrams - Example 1 Initially, put all tasks at their earliest possible time. A B A, B and C can all start at time zero. C D E F G Hours 2 4 6 8 10 12 14 16

  3. Cascade diagrams - Example 1 D can start immediately after A finishes. A B C D E F G Hours 2 4 6 8 10 12 14 16

  4. Cascade diagrams - Example 1 E and F can start immediately after B finishes. A B C D E F G Hours 2 4 6 8 10 12 14 16

  5. Cascade diagrams - Example 1 G is dependent on C, D and E, so it can start after D finishes. A B C D E F G Hours 2 4 6 8 10 12 14 16