LCA Project Delivery Team Management Meeting February 13, 2014. ; ; ; ; . LCA PDT Project Status Report . Project Name: LCA Barataria Basin Barrier Shoreline (BBBS) PED PMs: State – Brad Miller Corps – Steve Keen Basin(s ): Barataria
E N D
LCA Project Delivery Team Management Meeting February 13, 2014 ; ; ; ;
LCA PDT Project Status Report • Project Name: LCA Barataria Basin Barrier Shoreline (BBBS) PED • PMs:State – Brad Miller Corps – Steve Keen • Basin(s):Barataria • Related Projects – CIAP Caminada Headland Beach and Dune Restoration • Status (Schedule): • Scheduled Event(s)– • Chiefs Report: Signed 22Jun2012 • Design Agreement (DA): June 2014??? • Recent Event(s): • MVN is revising PMP and cost estimate to reflect reviewing the State’s design and construction of all beach and dune features as well as the design of @3.5 miles of marsh back-bay features. • NSE issues nearly resolved between USACE and State. • IDR submitted to MVD on 25Jul2013; approved by MVD on 08Sep2013. • Schedule Issue(s): NA
LCA PDT Project Status Report • Project Name: LCA MR Hydrodynamic & Delta Management Feasibility Study • PMs: Corps– Daimia Jackson/PFs–Cherie Price CPRA – Elizabeth Jarrell/Carol Parsons Richards • Basin(s): Mississippi River, Barataria, Pontchartrain, Breton Sound • Status (Draft Schedule): • The Alternatives Milestone IPR – June 2014 • Tentatively Selected Plan – August 2015 • Agency Decision Milestone Meeting – March 2016 • Final Report Milestone September – 2016 • Chief’s Report – December 2016 • Recent Event(s): • Delta Mgmt Component: • Study is kicking off after rescoping and restructuring with CPRA • PDT reinitiation kick off meeting was held Tuesday, 11 Feb 2014 • Revising PMP and developing & evaluating an initial array of alternatives • CPRA Delft 3D & EwE revised SOW received. COE is reviewing ($3.5M) • Hydro Component: • Year 3 work plans under development • Presenting all efforts at the State of the Coast Conference on March 19th and 20th • Geomorphic Group finalizing the report • 1D finishing up years 1-2 production runs & working on HEC-RAS model development • 2D (ADH) calibration & validation complete, FWOP complete, team is beginning production runs • 3D (Delft 3D) calibration & validation complete, team is beginning FWOP runs • Other: • N/A
LCA PDT Project Status Report Project Name: Small Diversion at Convent/Blind River PFs:State: Stephanie Zumo Corps: Danielle Tommaso PMs: State: Renee Bennett Corps: Steve Keen Basin(s): Lake Pontchartrain Related Projects: LCA Hope Canal Diversion, CWPPRA River Reintroduction into Maurepas Swamp, LCA Amite River Diversion Canal Spoil Bank, Gapping, CIAP Blind River Freshwater Diversion Status (Schedule): Next Milestones: PMP to CPRA done Data collection (borings, testing) on hold Design on hold Schedule & Budget Issues: All work on this project is suspended pending the resolution of the cross-crediting of WIK. PMP at CPRA for review/signature. Other: Review Plan approved December 2012.
LCA PDT Project Status Report • Project Name: SW Coastal LA Feasibility Study (State/Corps) • PFs: State: Norwyn Johnson Corps: Andrew MacInnes • PMs: State: Norwyn Johnson Corps: PJ Varnado • Basin(s): Sabine, Calcasieu, and Mermentau • Related Projects: This feasibility effort has many State/CWPPRA/CIAP existing and proposed projects within the three parish study area. • Status (Schedule): • The TSP milestones were conducted on Oct 28 & Nov 1, 2013 • Public/Policy/Technical review completed on Jan 26, 2014 (receipt of comments extended) • Response to all comments • Agency Decision Milestone scheduled for Mar 5, 2014 • Schedule Issue(s): • CWRB/Final Report Milestone on Jul 10, 2014 • Signed Chief’s Report Milestone on Sep 30, 2014 • Additional evaluation of structural & nonstructural alternatives • Budget Issue(s): Not in President’s 2014 Budget (Corps has allocated funds to complete the study)