RICH WG Meeting. M. Lenti July 13, 2011. Mirror Support System. On June 23 myself and Enrico visited Vito Carassiti in Ferrara Since mid-september Vito will work on engeneering the Mirror Support System starting from the study made until now

dillan
Download Presentation

RICH WG Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RICH WG Meeting M. Lenti July 13, 2011

  2. MirrorSupport System • On June 23 myself and Enrico visited Vito Carassiti in Ferrara • Sincemid-september Vito will work on engeneering the MirrorSupport System startingfrom the studymadeuntilnow • Closecontactwith Vito mandatory!

  3. PM relatedmechanics July 7, 2011 N.4 800x800x40 mm3 N.2 800x800x30 mm3 AluminumAnticorodal 6082-T6 Nextweeks: fromsquarestodisks (external company) FromSeptember: full machining In the Universityworshop

  4. Winston Cones Disk F.Maletta Number and position ofholesonly indicative: SeeF.Bucci’s presentation 2 disks: Jura side and Saleve side

  5. PM Lodgingdisks F.Maletta PM lodgingholesnotshown 2 disks: Jura side and Saleve side

  6. VacuumProtectionDisks Keep the vacuum on one side Plug the PM lodging disk on the opposite side 2 disks: Jura side and Saleve side

  7. Quartz Windows • Procurement procedure started (PG will care about) • 2100 12.7 mm diam., 1 mm thickquartz windows in order

  8. Gas system Dear Massimo,Following the discussion you had with Stefan and Frederic concerning the gassystem for the na62 rich, we evaluate the following price for the secondversion (i.e. the detector is a vacuum vessel):-) gas system: 220 kCHF-) Ne recuperation unit (optional): 80 kCHFThe price includes all the installation work needed (racks installation anddetector connection to the gas system).You can find in attachment the drawing for the last version.We are available if you would like to discuss in more detail the gas system.Best regards,Frederic, Roberto

  9. Gas System

  10. Gas System Dear Roberto and Frederic, Thank you very much for this drawing and for the estimate. I have a few comments/questions to the scheme: For the names and locations: you could consider the following changes:o UX -> ECN3o Mixer in Surface -> Gas area in B918o The battery should go to B920 (gas storage area) I am not sure I understand the pump module in the UX. When you empty the tank for recovery you would still need a vacuum pump ? In the minimal system, without gas recovery , one wouldn't need the UX pump module (except for a vacuum pump), neither the pump module in the surface. Is that correct? Although, we think at this stage it is not required, we should keep in mind the possible option of gas re-circulation and purification. I think, one would probably want a purge outlet with a big bubbler (separated by manual valve) for flushing during shut-downs (perhaps, just before YV 6127). Pipework: Some pipes indicated on the drawing (e.g. Ø=22 from B918 to ECN3) don't exist. It would be good identify exactly what can be re-used from existing pipes and what must be installed new. The Air supply should be clean air from a battery and the Air supply in ECN3 needs to be created (one could re-use one of the existing small diameter pipes)Regarding the schedule, it would be good if the system can be installed in spring 2012. Cheers, Ferdi