301 likes | 494 Views
LOAD ANGLE MEASUREMENT USING SCADA A UNIQUE VISUALISATION TOOL FOR GRID OPERATION. S.P.KUMAR CM(SCADA-IT) SRLDC, POWER GRID. NATIONAL GRID QUICK FACTS. REGIONAL GRIDS. INSTALLED CAPACITY NORTHERN :- 33,782 MW EASTERN :- 16,680 MW SOUTHERN :- 37,054 MW
E N D
LOAD ANGLE MEASUREMENT USING SCADA A UNIQUE VISUALISATION TOOL FOR GRID OPERATION S.P.KUMAR CM(SCADA-IT) SRLDC, POWER GRID
REGIONAL GRIDS INSTALLED CAPACITY NORTHERN :- 33,782 MW EASTERN :- 16,680 MW SOUTHERN :- 37,054 MW WESTERN :- 34,867 MW NORTH-EASTERN :- 2,443 MW TOTAL(APPROX) 125,000 MW NORTHERN REGION NORTH-EASTERN REGION EASTERN REGION WESTERNREGION SOUTHERN REGION
‘ELECTRICAL’ REGIONS NORTHERN REGION 1 NORTH-EASTERN REGION EASTERN REGION WESTERNREGION 2 SOUTHERN REGION WITH THE COMMISSIONING OF THE TALA PROJECT CONNECTING THE EASTERN AND NORTHERN GRIDS, INDIA WILL HAVE ONLY TWO GRIDS
Installed capacity & Inter regional links Two synchronous systems -North-Central & South 30,500 MW 34,307 MW 2,404 MW 16,478 MW 16,000 37,140 MW 36,584 MW Installed Generation Capacity Current : 126,994 MW Target for Year 2012 : 200,000 MW Figures as on 31-Aug-2006
Hydro Coal Energy Resource Map
ANDHRA PRADESH KARNATAKA TAMIL NADU KERALA SOUTHERN REGION – GEOGRAPHY POPULATION :- 22.5 CRORES ( 22% OF INDIA) AREA :- 651 (‘000 SQ KM)(19% OF INDIA) INSTALLED CAPACITY:- 36,784 MW(29.5%) WEATHER :- South-west monsoon North-east monsoon SEA COAST :- AROUND 4000 KM
GENERATING UNITS IN SOUTHERN REGION A.P TYPICAL GENERATOR SPREAD IN SR KAR - HYDRO - THERMAL KER TN GENERATORS ABOVE 1000 MW - GAS / NAPTHA GENERATORS 500 – 1000 MW - NUCLEAR GENERATORS BELOW 500 MW
TYPICAL LOAD SPREAD IN SR LOAD 500-1500 MW LOAD 200-500 MW
400KV SUB-STATIONS IN SR KALPAKKA RAMAGUNDAM SIMHADRI 1 GAZUWAKA KHAMMAM GMR VEMAGIRI HYDERABAD P P JEGRUPADU EXTN P MAMIDIPALLY P MEHA BOOB NAGAR VIJAYAWADA RAICHUR NAGARJUNASAGAR P SRI SAILAM MUNIRABAD P KURNOOL P GOOTY CUDDAPAH NARENDRA 60 P NELLORE DAVANAGERE KAIGA HIRIYUR CHITTOOR NELAMANGALA ALMATHI BANGALORE TALAGUPPA MADRAS KOLAR P -- OF POWERGRID P HOODY MYSORE HOSUR -- OF NTPC NEYVELI TPS I (EXP) 63 -- OF ANDHRA PRADESH SALEM P NEYVELI -- OF TAMIL NADU UDUMALPET TRICHY P -- OF KARNATAKA TRICHUR P P -- OF NLC P MADURAI -- OF NPC TRIVENDRUM
MONSOONS SOUTH WEST MONSOON NORTH EAST MONSOON BACK
SR QUICK FACTS • INSTALLED CAPACITY 37054 MW • THERMAL: HYDRO 67:33 • PEAK DEMAND MET ≈ 23,000 MW • MAX DAILY CONSUMPTION 525 MU
400KV GRID MAP OF SOUTHERN REGION ORISSA TALCHER BHADRAVATI JEYPORE MAHARASHTRA AP SIMHADRI RSTPP KALPAKKA P KHAMMAM GAZUWAKA MMDP HYDERABAD P VEMAGIRI P GMR MAHABOOB NAGAR GVK P VIJAYAWADA N’SAGAR NARENDRA RAICHUR P KAR KURNOOL MUNIRABAD SSLMM P KAIGA GOOTY 1000 MW HVDC BACK TO BACK LINK P N KADAPA P GUTTUR NELLORE 2000 MW HVDC BIPOLE HIRIYUR TALGUPPA NELAMANGALA `HOODY CHITTOOR 500 KV HVDC LINE MADRAS BANGALORE P KOLAR MAPS HOSUR 400 KV LINE POWERGRID 400 KV LINE APTRANSCO SALEM NEYVELI 400 KV LINE KPTCL NEYVELI TPS – 1 (EXP) TN 400 KV LINE OPERATED AT 220 KV UDUMALPET P TRICHY TRICHUR P THERMAL GENERATING STATION MADURAI 400KV SUB-STATION KER NUCLEAR STATION SRLDC, BANGALORE MARCH 2006 THIRUVANANTHAPURAM
Grid Performance Number of Grid Disturbances have come down High Transmission System Availability
LOAD ANGLE AN EMPIRICAL TOOL
POWER SYSTEM STABILITY • ‘Power system stability is the ability of an electric power system, for a given initial operating condition, to regain a state of operating equilibrium after being subjected to a physical disturbance, with most system variables bounded so that practically the entire system remains intact.’ ---------------------------------------VLPGO ’05, WG1
STABILITY CLASSIFICATION VLPGO 2005 WG1
WHY DO WE NEED A LOAD ANGLE DISPLAY ? • SOUTHERN REGION WAS PLAGUED BY LOW VOLTAGES, HEAVILY LOADED LINES, LOW FREQUENCY PROBLEMS • SKEWED LOADING ON LINES DUE TO LARGE DISTANCES BETWEEN LOAD AND GENERATION • OPERATOR COULD NOT PERCIEVE HOW NEAR TO THE PRECIPE HE WAS • SEPARATIONS/ GRID DISTURBANCES WAS THE ORDER OF THE DAY • INTER AREA OSCILLATIONS WERE NOTICED FREQUENTLY • DECREASING GENERATION/LOAD SHEDDING IN SELECTED PLACES HELPED ALLEVIATE THESE SYMPTOMS • LOAD ANGLE WAS CALCULATED AND STORED • MANY DISTURBANCES WERE ANALYSED AND AN EMPIRICAL LIMIT WAS CONCIEVED • LOAD ANGLE FOR EACH CRITICAL LINE AND CORRIDOR IS DISPLAYED
LOAD ANGLE- VISUAL DISPLAY • DATA FROM ALL STATIONS ARE AVAILABLE AT 10 SEC REFRESH RATE • COMPUTATION OF ANGLE IS DONE AT RSCC SERVER • LINE WISE AND CORRIDOR WISE LOAD ANGLE DISPLAY IS GIVEN TO OPERATOR • GENERALLY LIMITED TO 50O FOR CORRIDOR AND 20O FOR SINGLE HOP FOR CRITICAL LINKS
25 350KM line 200KM line 100KM line 20 15 10 5 0 100 200 300 400 500 600 LOADANGLE AND POWERLEVEL RELATION FOR DIFFERENT LINE LENGTHS Load Angle in degrees Power Level in MW
LOAD ANGLE OF RGM-NLY DURING A SYSTEM SEPARATION 80.0 SYSTEM SEPARATION POINT 70.0 60.0 50.0 LOAD ANGLE IN DEGREE 40.0 30.0 20.0 10.0 0.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 HOURS------------>
Inputs used • Vindhyachal North Bus L-L Voltage. • Angular Separation between Vindhyachal North Bus and West Bus. ( Available through Phase angle transducer having one input through R-Phase North Bus and another through R-Phase West Bus having range only up to 60 degree) • Phasor Voltage difference between Vindhyachal North Bus and West Bus ( Available through voltage transducer having one input through R-Phase North Bus and another through R-Phase West Bus)