Floating Machine D evelopment Week 40. R. Assmann for the LHC MD coordination team ( R. Assmann, Frank Zimmermann, Giulia Papotti ) LPC, 03.10.2011. Schedule. 4.10.: Discussion in LSWG with input / clarifications / requests from MD teams ( round-table )
E N D
Floating MachineDevelopment Week 40 R. Assmann for the LHC MD coordination team (R. Assmann, Frank Zimmermann, Giulia Papotti) LPC, 03.10.2011 R. Assmann
Schedule 4.10.: Discussion in LSWG withinput/clarifications/requestsfrom MD teams (round-table) 5.10.: Discussionofdraftlist in LMC Week 2.10.-8.10.: Large pile-up MD. Floating MD #1: 25ns setup Week 9.10.-15.10.: Floating MD #2: 25ns setup 18.10.: Discussion in LSWG with detailed presentations from MD teams. Start MP procedure. 19.10.: Discussion in LMC. Approval of plan for MD#4. MD#4: Oct 30, 6am - Nov 4, 6am. R. Assmann
Introduction • Scheduled 168h ofmore MD time in 2011: • 120h in MD block #4. • 48h in floatingMD‘s (scheduledduringphysicsrun). • Wecouldhavescheduledanother 230h (seelist) andmore (in yourrequeststhatwealreadyreduced)... • Not everythingcanbedone! • We will also have MD time in 2012! Will askfornewrequestsfornextyear, whichshouldtakeintoaccountresultsachieved in 2011. • All thisdepends on yourinputtous! R. Assmann
Present Draft List (to be discussed this week) This week To be moved to regular MD? R. Assmann
Present Draft List R. Assmann
Present Draft List R. Assmann
ReceivedRequests: Not Scheduled I R. Assmann
ReceivedRequests: Not Scheduled II R. Assmann
ReceivedRequests: Not Scheduled III R. Assmann
Present Draft List R. Assmann
Present Draft List R. Assmann
Discussion • Whatshould NOT bedoneandwhat MUST still bedone in 2011? • Scheduled 168h ofmore MD time in 2011. • Wecouldhavescheduledanother 230h (seelist) andmore (in yourrequeststhatwealreadyreduced)... R. Assmann
Thankyou... R. Assmann
Scheduled & not yet scheduled MD Requestsstatus August 2011 Appendix 1 – MD List (Status Aug. 2011) times in hours (incl. possible ramp down) allocated in: 1st MD block 2nd MD block 3rd MD block R. Assmann
beam-beam MD’s 8+17+16 8 1 6 (EOF) total: 134 h R. Assmann
optics MD’s 14+14 10 12 8 total: 98 h R. Assmann
e-cloud MD’s mC priority 7 total: 36 h R. Assmann
operational MD’s total: 12 h R. Assmann
IR MD’s 8 10 total: 32 h R. Assmann
injection & injection protection MD’s 8 6+7 9 (4+) 10 total: 111 h R. Assmann
collimation MD’s 4 5 10 mC priority 10 5 10+10 total: 72 h R. Assmann
MD’s on passive protection for stored beam total: 16 h R. Assmann
impedance MD’s 10 (5?) total: 48 h R. Assmann
R2E MD’s 8 total: 8 h R. Assmann
instrumentation MD’s 10 10 total: 31 h R. Assmann
RF MD’s 8+10 10 as operational development 8 6 total: 124 h R. Assmann
ion MD’s not ready? total: 26 h R. Assmann
experiment MD’s mC priority 6 in MD block 4? total: 12 h R. Assmann
magnet MD’s 6 6+4 not in MD total: 41 h R. Assmann
EOF studies R. Assmann
operational development studies R. Assmann