1 / 33

SYSTEMS ANALYSIS & DESIGN

SYSTEMS ANALYSIS & DESIGN. PHASE 4 SYSTEMS IMPLEMENTATION Installation and Evaluation. Chapter 11. Installation and Evaluation. Objectives. Discuss the main tasks in the installation and evaluation process Explain why it is important to maintain separate operational and test environments

dixon
Download Presentation

SYSTEMS ANALYSIS & DESIGN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SYSTEMS ANALYSIS & DESIGN PHASE 4 SYSTEMS IMPLEMENTATION Installation and Evaluation

  2. Chapter 11 Installation and Evaluation

  3. Objectives • Discuss the main tasks in the installationand evaluation process • Explain why it is important to maintain separate operational and test environments • Develop an overall training plan with specific objectives for each group of participants • Explain three typical ways to provide training, including vendors, outside resources, and in-house staff

  4. Objectives • Describe online tutorials and other user training techniques • Create an outline for a training manual and describe the contents of each section • Describe the file conversion process • Identify four system changeover methods and discuss the advantages and disadvantages of each

  5. Objectives • Explain the purpose of a post-implementation evaluation and list the specific topics covered during the evaluation • Specify the contents of the final report to management

  6. Introduction • Installation and evaluation completes the systems implementation phase • The new system is now ready to be used • Remaining tasks • Prepare an operational environment and install the new system • Provide training for users, IS staff, and managers • Perform file conversion and system changeover • Carry out post-implementation evaluation • Present a final report to management

  7. Click to see Figure 11-1 Click to see Figure 11-2 Operational and Test Environments • Test environment • Programmers and analysts use the test environment to develop and maintain programs • The test environment contains copies of • Programs • Procedures • Test data files

  8. Operational and Test Environments • Operational environment • Also called the production environment • Access is limited to information system users • IS staff enter the production environment only to correct problems or perform authorized work • Live, actual data is used • All changes must be verified and user approval obtained

  9. Operational and Test Environments • Preparation of the operational environment • Examine all system components that affect system performance • Hardware and software configurations • Operating system programs and utilities • Network resources • Check all communications features, both before and after loading programs • Include network specifications in documentation

  10. Click to see Figure 11-3 Click to see Figure 11-4 Training • A training plan should be consideredearly in the systems development process • Specific training is necessary for • Users • Managers • IS department staff members

  11. Click to see Figure 11-5 Training • Vendor training • If hardware or software is purchased outside, vendor training should be considered • Many vendors offer free or nominal cost training for customers • Vendor training can be performed at the vendor’s site or at the customer’s location • Vendor training often provides the best return on training dollars

  12. Click to see Figure 11-6a Click to see Figure 11-6b Training • Outside training resources • If vendor training or internal training is impractical, outside trainers or consultants can be used • Outside training generally is not practical for in-house developed systems • Many sources of training information exist • Consultants • Universities • Information management organizations • Industry associations

  13. Training • In-house training • IS staff and user departments usually share responsibility for developing and conducting training for in-house systems • Training techniques can include many techniques and training aids, including multimedia, demonstrations, videotapes, and charts

  14. Click to see Figure 11-7 Training • In-house training • Some guidelines to consider • Train people in groups, with separate programs for distinct groups • Select the most effective place for training • Provide for learning by hearing, seeing, and doing • Prepare a training manual

  15. Click to see Figure 11-8a Click to see Figure 11-8b Training • Some guidelines to consider • Train people in groups, with separate programs for distinct groups • Select the most effective place for training • Provide for learning by hearing, seeing, and doing • Prepare a training manual • Develop interactive tutorials and training tools • Rely on previous trainees • When training is complete, conduct a full-scale simulation for users to gain experience and confidence

  16. Click to see Figure 11-9a Click to see Figure 11-9b Training • Some guidelines to consider • Train people in groups, with separate programs for distinct groups • Select the most effective place for training • Provide for learning by hearing, seeing, and doing • Prepare a training manual • Develop interactive tutorials and training tools • Rely on previous trainees • When training is complete, conduct a full-scale simulation for users to gain experience and confidence

  17. File Conversion • File conversion can take place after the operational environment is established and training has been performed • Issues to consider • Automated conversion techniques • Methods of exporting data to the new system • Programs designed to extract and convert data • Controls required to protect vulnerable data • Verification of results by users

  18. Click to see Figure 11-10 System Changeover • System changeover puts the new system online and retires the old system • Four typical approaches exist • Direct cutover • Parallel operation • Pilot operation • Phased changeover • Each approach involves different cost and risk factors

  19. Click to see Figure 11-11 System Changeover • System changeover puts the new system online and retires the old system • Four typical approaches exist • Direct cutover • Parallel operation • Pilot operation • Phased changeover • Each approach involves different cost and risk factors

  20. System Changeover • Direct cutover • With direct cutover, changeover from the old system to the new system occurs immediately, as the new system becomes operational • Cost is relatively low because only one system is in operation • Risk is relatively high because there is no backup option • Timing is an important factor for systems that have periodic processing cycles

  21. System Changeover • Parallel operation • With parallel operation, both the new and the old systems operate fully for a specified period • Data is input to both systems, and results can be verified • Cost is relatively high, because both systems operate for a period of time • Risk is relatively low, because results can be verified and a backup option exists • Method is impractical if the systems are dissimilar or cannot be supported together

  22. System Changeover • Pilot operation • With pilot operation, both the new and the old systems operate, but only at a selected location, called a pilot site • The rest of the organization continues to use the old system • Cost is relatively moderate, because only one location runs both systems • Risk also is relatively moderate, because the new system is installed only at the pilot site and the risk of failure is reduced

  23. System Changeover • Phased changeover • With phased changeover, the system is implemented in stages, or modules across the organization • Phased changeover gives part of the system to entire organization • Cost is relatively moderate, because the system is implemented in stages, rather than all at once • Risk also is relatively moderate, because the risk is limited to the module being implemented

  24. Click to see Figure 11-12 Post-Implementation Evaluation • After the system is operational, two main tasks must be performed • Post-implementation evaluation • Final report to management

  25. Click to see Figure 11-13 Post-Implementation Evaluation • Post-implementation evaluation feedback • Includes various areas • Accuracy, completeness, and timeliness of output • User satisfaction • System reliability and maintainability • Adequacy of system controls and security • Hardware efficiency/platform performance • Effectiveness of database implementation • Performance of the IS team • Completeness and quality of documentation • Quality and effectiveness of training • Accuracy of cost-benefit estimates and development schedules

  26. Post-Implementation Evaluation • A post-implementation evaluation is basedon fact-finding methods similar to techniques used during the systems analysis phase • Ideally, post-implementation evaluation should be performed by people who were not involved in the development process • Usually done by IS staff and users • Internal or external auditors often are involved

  27. TRADEOFF • When should post-implementation evaluation occur — how soon after system operation begins? • If too long, users remember less about the development process and how it might be improved • If too soon, users have insufficient time to assess system strengths and weaknesses • Six months of operation is desirable, but pressure to finish sooner often exists

  28. A KEY QUESTION • At Yorktown Industries, Cindy Winslow needs your advice • The new human resources system was finished under budget and ahead of schedule • Cindy's boss wants her to handle the post-implementation evaluation, even though she headed the development effort for this project • Cindy comes to you for advice — what should she do?

  29. Final Report to Management • Report contents 1. Final versions of all system documentation 2. Planned modifications and enhancements to the system that have been identified 3. A recap of all systems development costs and schedules 4. A comparison of actual costs and schedules to the original estimates 5. The post implementation evaluation, if it has been performed

  30. SOFTWEAR, LIMITED • The payroll package from Pacific Software has been implemented, and the ESIP system installation is ready to begin • Perform installation tasks for the ESIP system extract module • Confirm SWL’s network can handle the load • Install the ESIP application on the payroll server • Check server and mainframe communication • Test the extract module, and confirm that the mainframe generates and downloads the proper data file to the ESIP server

  31. SOFTWEAR, LIMITED • Perform training tasks • Conduct training session with the payroll group • Explain the user manual • Answer questions and obtain user feedback • Establish security levels • Set up password and authorization for director of human resources to modify ESIP options • Provide security documentation, which is not printed in the user manual

  32. SOFTWEAR, LIMITED • Verify processing results • Use test data with errors purposely inserted • Continue manual handling of ESIP deductions • Select and carry out system changeover • Perform direct cutover, in connection with the weekly payroll cycle on May 7, 1999 • Verify all results • Obtain feedback from all users • Update documentation and complete direct cutover procedures

  33. Click to see Figure 11-14 SOFTWEAR, LIMITED • Conduct post-implementation evaluation • Evaluation scheduled after successfully completing eight weekly payroll cycles and two monthly deduction transfers • The evaluation team was not involved in ESIP system project (one IS member, one from finance department) • Team performed various fact-finding tasks • Final report was prepared and sent to management

More Related