270 likes | 286 Views
Presentation to the Board of Selectman outlining causes, design solutions, timeline, funding, and collaboration with Cambridge on Winn’s Brook sewer overflow mitigation project.
E N D
TOWN OF BELMONT Presentation to the BOARD OF SELECTMAN December 7, 2009 WINN’S BROOK SEWER OVERFLOW MITIGATON
Presentation Objectives • Project background • Causes of sewer overflows • Conceptual design and modeling • Final Design • Opinion of probable construction cost • Funding • Schedule
Winn’s Brook Area • Low lying area in Northeast Belmont • Close proximity to MWRA connection on Flanders Road • 85% of Belmont tributary to Flanders Road • Extensive upstream sewer system • Two different sewer subsystems
The Problem Periodic sanitary sewer overflows and backups into basements of homes in the Winn’s Brook Area
Causes of an IncreasedHydraulic Grade Line (HGL) • System Capacity Constraints • Infiltration/Inflow in Belmont • 2007 Flow Monitoring Program • Elevated downstream HGL • Flanders Road Connection to the MWRA
Project Timeline • 2005 – Geographical Information System (GIS) • InfoWorks Sewer Model • Used by Cambridge & MWRA • 2006 – Winn’s Brook Area Study • 2007 – State (SRF) Loan Application • 2009 – Final Design
Solution Constraints • No transference of the problem to Cambridge or significant increase in flow to MWRA interceptor • No transference of problem within Belmont • Continued I/I reduction will be required • 2009 Sewer System Evaluation Survey
Mitigation Concepts • Increase sewer capacity • Flow diversion • Storage • Isolation and Pumping • I/I Removal • 13 Mitigation Alternatives Modeled
Collaboration with the City of Cambridge • Cambridge integrated Belmont’s model into the complete downstream system model • Key in refining the selected Alternative • NO ADVERSE IMPACT TO CAMBRIDGE • NO INCREASED CSO RELEASE (MWRA)
Selected Alternative No. 12 • Isolate Winn’s Book Area during elevated HGL conditions • New sewers and diversion structures • Divert flow to an off-line pumping station • Divert upstream flow • Dean Street • Leonard Street & Alexander Ave. • In-line storage conduit (Dean St) • Restricted discharge • 15% Townwide I/I reduction
Predicted Impact at Key Manholes Outside Winn’s Brook Area(MH rim to HGL)
Project Funding • $11.6 M State Revolving Loan (SRF) • ARRA “Shovel Ready” Projects • Contract 1 – Wellington Brook Area Sewer and Storm Drain Improvements • Contract 2 – Stony Brook Road and Woodbine Road Pump Station Replacement • Contract 3 – Winn’s Brook Area Sewer Overflow Mitigation
Winn’s Brook – Contract 3Construction Schedule 11/25/2009 - Advertised for Bid 12/21/2009 - Bids Received 01/15/2010 - Contract Execution 02/01/2010 - Notice to Proceed 07/31/2011 - Construction Complete (18 months)
Questions? Justin Gould, P.E.Fay, Spofford & Thorndike